CLAS12 R1 Progress Reports

From New IAC Wiki
Jump to navigation Jump to search

The Drift Chamber Wiki at JLab

CLAS12 Web page

1) Dial toll free, 866-740-1260 2) Enter the 7 digit Access Code, 6074391, followed by the "#" key.


ODUs logbook


Database Viewer


or if the DAQ computer is at the IAC

Database Viewer

service httpd start

Clean room Prep

CleanRoomPrep2009-2011

Clean room Construction 2011

CleanRoomConstruction2011

Jlab Shipment 8/8/2011

JLabShipment08082011

Jlab Stringing Prep

CLAS12_CleaRoomPrep_2011

September 2011

201109_R1ProgressRep

October 2011

201110_R1ProgressRep

November 2011

201111_R1ProgressRep

December 2011

201112_R1ProgressRep

January 2012

201201_R1ProgressRep

February 2012

201202_R1ProgressRep

March 2012

201203_R1ProgressRep


CLAS12_R1

ISU - Clean Room Particle Count Log


April 2012

201204_R1ProgressRep


CLAS12_R1

ISU - Clean Room Particle Count Log


May 2012

201205_R1ProgressRep


CLAS12_R1


June 2012

201206_R1ProgressRep


CLAS12_R1


July 2012

201207_R1ProgressRep


CLAS12_R1


August 2012

201208_R1ProgressRep


CLAS12_R1


September 2012

201209_R1ProgressRep

JLab Shipment

09122012_JlabShipment

925R1SL1S5 FieldTensionCompare.png

925R1SL1S6 SenseTensionCompare.png

CLAS12_R1


October 2012

201210_R1ProgressRep


Potting

Epoxy Ratio 2.33:1 (Epon 828 Resin : Versamid 140).


CLAS12_R1


November 2012

201211_R1ProgressRep

December 2012

201212_R1ProgressRep

12/3/12 Meeting Notes with Mac and George at ISU

Construction Proceedures:

Chambers outside cleanroom should have covers to keep dust off buss wires

Cap 113 (Brown one) needs to be replaced on STB board.


Need 2 amp fuse on 5 Volt supply to pre-amps.

operate chamber STB voltage at 6 Volts


Chamber grounding (ground through HV cable)

Chamber operating procedures

1.) post amplifier in VME crate had 150 mV peak-peak noise

2.) Stop using the current ADB crate

3.) New nominal Voltages from Mac are

S:F:G = 1300:-650:

S/F = 2

S/G = 5/7

Signal output doubles every 75 Volts difference between sense and field


4.) Discriminator level for signals:

5.) Need to lower the HV trip current back to 1 microA. May increase it to 5 micro Amps when burning in.

6.) Change trip speed to 0.1 sec



ISU Tasks:

1.) Install cover on top of chamber, top could be made from home insulation sheets that has been covered with paper or plastic sheeting.


2.) Install 208 Volts for ADB crates that will be sent by JLab to replace the one they have given us.

3.) solder jumpers onto HV boards, install them in January when George returns

4.) Mylar window on S1 chamber needs to have some tape and weather stripping redone or modified

5.) Get allen head 3/32 for torque wrench, remember to replace brass screws if they are removed for some reason

6.) do not do final instrumentation, purge covers, and dust covers on the last 2 chambers until checking with JLab, the may want to survey them after delivery


JLab Tasks

1.) What are the fault conditions on the STB board when the power supply exceeds voltage/current

2.) Need signal cables with strain relief connects that have the shielding wrap grounded on the STB board but not grounded on the DAQ cabinet


3.) George will send purge covers and come back in January to install


January 2013

201301_R1ProgressRep


February 2013

201302_R1ProgressRep

March 2013

201303_R1ProgressRep


PCR Temps Sept2012-March2013.png

April 2013

201304_R1ProgressRep

May 2013

201305_R1ProgressRep

June 2013

201306_R1ProgressRep

July 2013

201307_R1ProgressRep

August 2013

201308_R1ProgressRep

September 2013

201309_R1ProgressRep


PCR Temps March-Aug-2013.png

October 2013

201310_R1ProgressRep

November 2013

201311_R1ProgressRep

December 2013

201312_R1ProgressRep

January 2014

201401_R1ProgressRep


JLab shipment

Plan: Lift chambers + Pallets out of Physics and carry them to ISU's loading dock using a fork lift on Wednesday January 8 when ISU is on Thanksgiving break. The chambers will be stored inside a heated building over thanksgiving break and be ready for pickup.

Rick at Partner Steel needs to be called in December with a final date

A fork lift reservation needs to be confirmed with Wade in December.


CLAS12_R1

February 2014

201402_R1ProgressRep

March 2014

201403_R1ProgressRep

CLAS12_R1