201312 R1ProgressRep

From New IAC Wiki
Jump to navigation Jump to search

12/6/13

Goal: Ship 3 chambers to JLab (S5, S6, and S3 ) on Jan. 8, 2014

Ambition: ship S1 as well.


S3: stringing is done, one side is potted, last side in progress.

S2: now aligned to repair the last wires that are out of spec.

1 Pallet is assembled and ready for shipping, a second pallet is assemble but one boot remains to be installed.

Haitham has traced out dust covers for S5.

David - Finish potting S3 before Dec 9, install windows on S3 before Dec 16, move S3 to upper leave and have it crated by Dec 23, put S5 in its crate before Jan 6

Haitham - finish Q&A on S5 and then crate up S5

Derrick - Finish third pallet before Dec 16.


Trailer is 48 ft long.

Double check pallet length

12/13/13

Shipping progress: : Ship 3 chambers to JLab (S5, S6, and S3 ) loading truck on Jan. 7, 2014

Trailer is 48' long, drift chambers are about 10' long,

Pallets need to be 95" or less, we intend to cut them down to 92" wide.


S3: potting is done, windows installation this weekend

S2: no progress

2 Pallet is assembled and ready for shipping but need to cut off 4" so they are 92" wide for the truck

S5 dust cover installation begin today

David - move S3 to upper level by Dec 23, put S5 and S3 into their crates before Jan 6, return as much unneeded equipment as possible

Haitham - finish Q&A on S5 and then crate up S5

Derrick - Finish third pallet before Dec 16.


CLAS12_R1_Progress_Reports#December_2013