= 9/2/09=
+
1) Dial toll free, 866-740-1260
 +
2) Enter the 7 digit Access Code, 6074391, followed by the "#" key.
  
An array of temperature probes will be used to monitor the ISU clean room's temperature and humidity, with one probe being a temperature and humidity probe.
 
  
Five probes will be used for basic temperature monitoring.  These probes are the [http://www.sensatronics.com/index.php/industrial-probes/temperature.html Sensatronics's Standard Temperature Probe] and will cost $60.50 each.
+
[http://128.82.116.28:2342/ODU+DAQ/ ODUs logbook]
  
ISU already possesses the [http://www.sensatronics.com/index.php/industrial-probes/temperaturehumidity.html Sensatronics's Temperature-Humidity Combo Probe] which will be used to monitor the temperature  and  humidity in the center of the room.
 
  
The thermometer's analog output is converted  to a digital signal using the [http://www.sensatronics.com/index.php/industrial-monitors/model-em1.html Sensatronics Model EM1 Environmental Monitor].  This device supports up to 12 monitoring probes and has a built-in web server to transmit its data over the network upon request.  This device will cost $438.90.
+
[http://daq1.physics.isu.edu/cgi-bin/r1dc_dbPlotter.pl Database Viewer]
  
  
The total cost will be approximately $760.00 for temperature monitoring in the ISU clean room.  The temperature probes will allow for real time temperature monitoring with web access to the data.  This data will be plotted using the same system as the [http://brems.iac.isu.edu/mrtg/roomtemp.html BREMS cluster] located at ISU.
+
or if the DAQ computer is at the IAC
  
 +
[http://daq1.iac.isu.edu/cgi-bin/r1dc_dbPlotter.pl Database Viewer]
  
=12/3/09=
+
service httpd start
  
===Clean Room entry doors===
+
=Clean room Prep=
  
[[File:CleanRoomEntryDoor_12-3-09.jpg | 200 px]]
+
[[CleanRoomPrep2009-2011]]
  
These are the entryway doors donated by ON semiconductor for the ISU clean room.  They will be fitted together to form an air shower device for entering the clean room.
+
=Clean room Construction 2011=
  
===Temperature Monitoring===
+
[[CleanRoomConstruction2011]]
  
Continuous [http://hal.iac.isu.edu/cacti-graphs/graph_6.html temperature and humidity monitoring] has been performed in the ISU clean room for the past month.
+
=Jlab Shipment 8/8/2011=
  
The data  so far show a <math>\pm</math> 2 degree Fahrenheit temperature deviation in the clean room.  These fluctuations are within the accepted fluctuation deviation required for the construction of the R1 drift chambers.
+
[[JLabShipment08082011]]
  
The humidity has been fluctuated more than the temperature, but has remained consistently well below the 55% requirement.
+
= Jlab Stringing Prep=
  
===R2 Stringing Platform===
+
[[CLAS12_CleaRoomPrep_2011]]
  
[[File:StringingPlatform_12-3-09.pdf | 200 px]]
+
=September 2011=
  
Here is the design sent to ISU of the R2 stringing platform.  It is currently believed that it should fit in the ISU clean room for the purpose of stringing the R1 wire chambers.
+
[[201109_R1ProgressRep]]
  
=12/9/09=
+
=October 2011 =
 +
[[201110_R1ProgressRep]]
  
Received pdf schematics of the R2 Stringing platform.  It appears that it will be able to fit in the ISU clean room without a problem.  If the size could be reduced without sacrificing functionality, that would still be beneficial.
+
=November 2011=
 +
[[201111_R1ProgressRep]]
  
[[File:StringingPlatform_12-9-09.pdf | 200 px]]
+
=December 2011=
 +
[[201112_R1ProgressRep]]
  
Temp fluctuations in the Clean room appear to be +/- 6 degrees F.  There are no fans in the room yet to circulate air and the thermostat has not be set to minimize temperature fluctuations.  The air temperature outside the building has fluctuated from 60 to -12 degrees F.
+
=January 2012=
 +
[[201201_R1ProgressRep]]
  
[http://wiki.iac.isu.edu/index.php/CLAS12_R1]  Go Back to [[CLAS12_R1]]
+
=February 2012=
 +
[[201202_R1ProgressRep]]
  
=03/18/10=
+
=March 2012=
 +
[[201203_R1ProgressRep]]
  
So far for the clean room construction floor and design plans are almost finalized and will be posted by next Thursday (03/25/2010) and are not up this week due to a software problem cause from an Operation System Upgrade.
 
  
These designs will be similar to what has been previously posted.
+
[[ CLAS12_R1]]
  
As for temperature control, the graphs can be found [http://wiki.iac.isu.edu/index.php/Clean_Room_Temp_Sensor here].  As can be seen, the temperature has been roughly constant with only slight perturbations until the last couple of days.  This increase in temperature is probably due to the increase of temperature here in Pocatello.
+
[[ PhysicsCleanRoomParticleCountLog | ISU - Clean Room Particle Count Log]]
  
While within the accepted deviations, work will be done to ensure less fluctuations in temperature by working with Facility Services to get better temperature detection in the room.  Also, when the room is actually constructed, the walls should help prevent heat loss or gain inside the cleanroom environment to a greater degree.
 
  
==Materials and Supplies==
+
=April 2012=
 +
[[201204_R1ProgressRep]]
  
To construct the cleanroom at the ISU facility will require:
 
  
~1300 feet of Unistrut  -  ~$7,600.00 (This includes all the bolting material also)
+
[[ CLAS12_R1]]
~135 Ceiling Panels      -  ~$3,200.00
 
13 HEPA Filters          -  ~$9,400.00 (We are currently talking with ON Semiconductor for a possible donation of HEPA Filters)
 
74 Lights                -  ~$7,000.00
 
Particle Counters
 
Paint (non-leaching)
 
Furniture
 
Curtains                -  ~$5,800.00
 
Doors                    -  ~$  900.00
 
  
 +
[[ PhysicsCleanRoomParticleCountLog | ISU - Clean Room Particle Count Log]]
  
The list of further equipment needed with their estimated costs will be uploaded as soon as the information becomes available.
 
  
Construction of the ISU cleanroom is anticipated to start near the beginning of May 2010 and will employ 1 graduate student to supervise and help with the construction.  Several REU students that are coming to ISU, plus some upper division high school interns.  Construction will be under full swing from May 2010 with anticipated completion by August 2010.
+
=May 2012=
 +
[[201205_R1ProgressRep]]
  
Testing will then ensue to ensure that the cleanroom does meet ISO 10,000 standards.
 
  
=6/10/2010=
+
[[ CLAS12_R1]]
  
1.) Wire tension apparatus
 
  
A new technique (pulse method) is being developed for measuring the wire tension.  The wire is pinged every second.  The wire resonance is measured by a scope. The  scope does a FFT of the response.  Short wires are at a fast frequency but weak.  This requires sampling over many pings as the signal dies off quickly.  LOng wires vibrate so slowly that it is hard to measures the frequency.  Perhaps sampling the long wires over 1 ping is a better improvement.  Chris quevas has measured this and is not finding too much difference between using 1 or several pings.  Measurements take about 1 minute or less per wire.  THe goal is to measure 10 wires per minute as was done using the old technique.  The new technique is Labview friendly but it hasn't been implemented.  Right now the FFT is output to a text file.
+
=June 2012=
 +
[[201206_R1ProgressRep]]
  
Old tester needed 40 amp on magnet, new tester need 100 amps?
 
  
May need a second magnet to do the first half of the detector.
+
[[ CLAS12_R1]]
  
2.) Endplate Nomenclature
 
  
icol = column of 11 wires , lower col number is closer to the endplate
+
=July 2012=
 +
[[201207_R1ProgressRep]]
  
irow = row of wires smaller row number is closer to the target
 
  
ilayer = enplate identification, the guard wire that is closest to the target  (22 layers)
+
[[ CLAS12_R1]]
  
iwire = wire number within the icol, irow, ilayer (114 wires)
 
  
irow:3, 10, 226 col with 11 = 2490 wires in a chambers except for R2
+
=August 2012=
 +
[[201208_R1ProgressRep]]
  
  
 +
[[ CLAS12_R1]]
  
=3/24/11 Cutting Entry doors=
 
  
[[File:032411_CuttingDoor1.jpg | 200 px]][[File:032411_CuttingDoor2.jpg | 200 px]]
+
=September 2012=
 +
[[201209_R1ProgressRep]]
  
 +
==JLab Shipment==
  
=6/16/11=
+
[[09122012_JlabShipment]]
  
#R1 feedthroughs are glued in the endplate at JLab
+
[[File:925R1SL1S5_FieldTensionCompare.png || 200 px]]
#All guard wires are done on the first R1 at JLab
 
#Clean room has arrived in the basement
 
#ISU Facilities management is confirming our electrical and fire suppression service for the clean room
 
#ISU Facilities also wants a seismic calculation (to be sure the clean room does not collapse if there is an earthquake?)
 
  
=6/30/11=
+
[[File:925R1SL1S6_SenseTensionCompare.png || 200 px]]
  
#Ordered Gantry recommended by Bob Miller (AHS-2-10-14, 14' I-beam to ground and 90" wide: The top of the stringing stand is 13'5" and the chamber is 78" wide, I believe the chain stay to use on the chamber does not need to go to 13'
+
[[ CLAS12_R1]]
#Clean Room Temperatures are being monitored closely now.  The weekly average was 73.4 with a min of 71.8 and max of 74.6. (Looks like +/- 1 degree F is possible over a 24 hour period just need to keep people from changing the set point)
 
#Floor painting quote of $2.5k is in hand.  We are planning to use the resin-based epoxy called Armorseal1000.
 
#Duct work restricting entrance to clean room has been removed
 
#Quotes for Fire suppression system changes are in (~$4k).
 
#Particle Counter
 
##$3700 for [http://www.labcompare.com/958-Portable-Particle-Counter-Handheld-Particle-Counter/2509-Hand-Held-Laser-Airborne-Particle-Counters/ particle counter] with logging software (counts 0.5 and 5 micron)
 
## One with an EPICS driver on E-bay? http://compare.ebay.com/like/150500301106?var=lv&ltyp=AllFixedPriceItemTypes&var=sbar
 
  
  
=7/7/11=
+
=October 2012=
 +
[[201210_R1ProgressRep]]
  
#All equipment has been removed from the clean room area so the floor can be painted.
 
#The painters should begin prepping the floor today
 
#The JLab particle counter has been ordered
 
#e-mail when the fire suppression and seismic stuff is confirmed.
 
#JLab has 1 scissor lift, do we need 2 here by Aug 18?
 
#Below is a picture taken while the floor is being prepared for painting
 
  
[[File:ACleanRoomPrep_4-7-11A.jpg | 200 px]][[File:BCleanRoomPrep_4-7-11.jpg | 200 px]]
+
==Potting==
  
=7/14/11=
+
Epoxy Ratio 2.33:1 (Epon 828 Resin : Versamid 140).
  
  
Preparing to raise the clean room.
 
  
1.) Floor protective mats from  [http://www.ramboard.com/index.php Ram Board].  BMC West in Idaho Falls has 2 rolls (38" x 100' @ $57.03 each)
+
[[ CLAS12_R1]]
  
2.) Rent 2 scissor lifts from pro rental (233-4770).  $150/weeks each
 
  
3.) Rent a crane from Rick @Partner Steel (233-2371) $85/hr to lower the lifts into the basement.  (Partner steel gives ISU hourly rates)
+
=November 2012=
 +
[[201211_R1ProgressRep]]
  
 +
=December 2012=
 +
[[201212_R1ProgressRep]]
  
Below are pictures of the freshly painted clean room floor.
+
==12/3/12 Meeting Notes with Mac and George at ISU==
  
  
 +
===Construction Proceedures:===
  
[[File:ACleanRoomPrep_4-14-11A.jpg | 200 px]][[File:BCleanRoomPrep_4-14-11.jpg | 200 px]]
+
Chambers outside cleanroom should have covers to keep dust off buss wires
  
 +
Cap 113 (Brown one) needs to be replaced on STB board.
  
=7/15/11=
 
  
Removing the 1 ton crane:
+
Need 2 amp fuse on 5 Volt supply to pre-amps.
  
[[File:CR_crane_7-14-2011a.jpg| 200 px]][[File:CR_crane_7-14-2011b.jpg| 200 px]][[File:CR_crane_7-14-2011c.jpg| 200 px]][[File:CR_crane_7-14-2011d.jpg| 200 px]]
+
operate chamber STB voltage at 6 Volts
  
  
=7/18/11=
 
  
Got organized to install the main frame
+
Chamber grounding (ground through HV cable)
  
 +
===Chamber operating procedures===
  
[[File:CR_Frame_7-18-2011a.jpg| 200 px]]
+
1.) post amplifier in VME crate had 150 mV peak-peak noise
  
=7/19/11=
+
2.) Stop using the current ADB crate
  
3-D removed water lines that were in the way.
+
3.) New nominal Voltages from Mac are
  
=7/20/11=
+
S:F:G = 1300:-650:
  
ISU's facilities people remove the  ceiling  lights (Kent 380-9814)
+
S/F = 2
  
[[File:CR_Lights_7-20-2011a.jpg| 200 px]][[File:CR_Lights_7-20-2011b.jpg| 200 px]]
+
S/G = 5/7
  
Put up 2  main frame beams.
+
Signal output doubles every 75 Volts difference between sense and field
  
[[File:CR_Frame_7-20-2011a.jpg| 200 px]][[File:CR_Frame_7-18-2011c.jpg| 200 px]][[File:CR_Frame_7-18-2011b.jpg| 200 px]]
 
  
=7/21/11=
 
  
Complete the Main support frame
+
4.) Discriminator level for signals:
  
[[File:CR_Frame_7-21-2011a.jpg| 200 px]][[File:CR_Frame_7-21-2011c.jpg| 200 px]][[File:CR_Frame_7-21-2011b.jpg| 200 px]]
+
5.) Need to lower the HV trip current back to 1 microA. May increase it to 5 micro Amps when burning in.
  
 +
6.) Change trip speed to 0.1 sec
  
  
[http://wiki.iac.isu.edu/index.php/CLAS12_R1] [[ CLAS12_R1]]
+
 
 +
 
 +
===ISU Tasks:===
 +
 
 +
1.) Install cover on top of chamber,  top could be made from home insulation sheets that has been covered with paper or plastic sheeting.
 +
 
 +
 
 +
2.) Install 208 Volts for ADB crates that will be sent by JLab to replace the one they have given us.
 +
 
 +
3.) solder jumpers onto HV boards, install them in January when George returns
 +
 
 +
4.) Mylar window on S1 chamber needs to have some tape and weather stripping redone or modified
 +
 
 +
5.) Get allen head 3/32 for torque wrench, remember to replace brass screws if they are removed for some reason
 +
 
 +
6.) do not do final instrumentation, purge covers, and dust covers on the last 2 chambers until checking with JLab, the may want to survey them after delivery
 +
 
 +
 
 +
 
 +
===JLab Tasks===
 +
 
 +
1.) What are the fault conditions on the STB board when the power supply exceeds voltage/current
 +
 
 +
2.) Need signal cables with strain relief connects that have the shielding wrap grounded on the STB board but not grounded on the DAQ cabinet
 +
 
 +
 
 +
3.) George will send purge covers and come back in January to install
 +
 
 +
 
 +
=January 2013=
 +
[[201301_R1ProgressRep]]
 +
 
 +
 
 +
=February 2013=
 +
 
 +
[[201302_R1ProgressRep]]
 +
 
 +
=March 2013=
 +
 
 +
[[201303_R1ProgressRep]]
 +
 
 +
 
 +
[[File:PCR_Temps_Sept2012-March2013.png | 200 px]]
 +
 
 +
=April 2013=
 +
 
 +
[[201304_R1ProgressRep]]
 +
=May 2013=
 +
 
 +
[[201305_R1ProgressRep]]
 +
 
 +
=June 2013=
 +
 
 +
[[201306_R1ProgressRep]]
 +
=July 2013=
 +
 
 +
[[201307_R1ProgressRep]]
 +
 
 +
=August 2013=
 +
 
 +
[[201308_R1ProgressRep]]
 +
=September 2013=
 +
 
 +
[[201309_R1ProgressRep]]
 +
 
 +
 
 +
[[File:PCR_Temps_March-Aug-2013.png | 200 px]]
 +
 
 +
=October 2013=
 +
 
 +
[[201310_R1ProgressRep]]
 +
=November 2013=
 +
 
 +
[[201311_R1ProgressRep]]
 +
=December 2013=
 +
 
 +
[[201312_R1ProgressRep]]
 +
=January 2014=
 +
 
 +
[[201401_R1ProgressRep]]
 +
 
 +
 
 +
==JLab shipment==
 +
 
 +
Plan:  Lift chambers + Pallets out of Physics and carry them to ISU's loading dock using a fork lift on Wednesday January 8 when ISU is on Thanksgiving break.  The chambers will be stored inside a heated building over thanksgiving break and be ready for pickup.
 +
 
 +
Rick at Partner Steel needs to be called in December with a final date
 +
 
 +
A fork lift reservation needs to be confirmed with Wade in December.
 +
 
 +
 
 +
 
 +
[[CLAS12_R1]]
 +
 
 +
=February 2014=
 +
 
 +
[[201402_R1ProgressRep]]
 +
=March 2014=
 +
 
 +
[[201403_R1ProgressRep]]
 +
 
 +
[[CLAS12_R1]]

Latest revision as of 16:27, 7 March 2014

The Drift Chamber Wiki at JLab

CLAS12 Web page

1) Dial toll free, 866-740-1260 2) Enter the 7 digit Access Code, 6074391, followed by the "#" key.


ODUs logbook


Database Viewer


or if the DAQ computer is at the IAC

Database Viewer

service httpd start

Clean room Prep

CleanRoomPrep2009-2011

Clean room Construction 2011

CleanRoomConstruction2011

Jlab Shipment 8/8/2011

JLabShipment08082011

Jlab Stringing Prep

CLAS12_CleaRoomPrep_2011

September 2011

201109_R1ProgressRep

October 2011

201110_R1ProgressRep

November 2011

201111_R1ProgressRep

December 2011

201112_R1ProgressRep

January 2012

201201_R1ProgressRep

February 2012

201202_R1ProgressRep

March 2012

201203_R1ProgressRep


CLAS12_R1

ISU - Clean Room Particle Count Log


April 2012

201204_R1ProgressRep


CLAS12_R1

ISU - Clean Room Particle Count Log


May 2012

201205_R1ProgressRep


CLAS12_R1


June 2012

201206_R1ProgressRep


CLAS12_R1


July 2012

201207_R1ProgressRep


CLAS12_R1


August 2012

201208_R1ProgressRep


CLAS12_R1


September 2012

201209_R1ProgressRep

JLab Shipment

09122012_JlabShipment

925R1SL1S5 FieldTensionCompare.png

925R1SL1S6 SenseTensionCompare.png

CLAS12_R1


October 2012

201210_R1ProgressRep


Potting

Epoxy Ratio 2.33:1 (Epon 828 Resin : Versamid 140).


CLAS12_R1


November 2012

201211_R1ProgressRep

December 2012

201212_R1ProgressRep

12/3/12 Meeting Notes with Mac and George at ISU

Construction Proceedures:

Chambers outside cleanroom should have covers to keep dust off buss wires

Cap 113 (Brown one) needs to be replaced on STB board.


Need 2 amp fuse on 5 Volt supply to pre-amps.

operate chamber STB voltage at 6 Volts


Chamber grounding (ground through HV cable)

Chamber operating procedures

1.) post amplifier in VME crate had 150 mV peak-peak noise

2.) Stop using the current ADB crate

3.) New nominal Voltages from Mac are

S:F:G = 1300:-650:

S/F = 2

S/G = 5/7

Signal output doubles every 75 Volts difference between sense and field


4.) Discriminator level for signals:

5.) Need to lower the HV trip current back to 1 microA. May increase it to 5 micro Amps when burning in.

6.) Change trip speed to 0.1 sec



ISU Tasks:

1.) Install cover on top of chamber, top could be made from home insulation sheets that has been covered with paper or plastic sheeting.


2.) Install 208 Volts for ADB crates that will be sent by JLab to replace the one they have given us.

3.) solder jumpers onto HV boards, install them in January when George returns

4.) Mylar window on S1 chamber needs to have some tape and weather stripping redone or modified

5.) Get allen head 3/32 for torque wrench, remember to replace brass screws if they are removed for some reason

6.) do not do final instrumentation, purge covers, and dust covers on the last 2 chambers until checking with JLab, the may want to survey them after delivery


JLab Tasks

1.) What are the fault conditions on the STB board when the power supply exceeds voltage/current

2.) Need signal cables with strain relief connects that have the shielding wrap grounded on the STB board but not grounded on the DAQ cabinet


3.) George will send purge covers and come back in January to install


January 2013

201301_R1ProgressRep


February 2013

201302_R1ProgressRep

March 2013

201303_R1ProgressRep


PCR Temps Sept2012-March2013.png

April 2013

201304_R1ProgressRep

May 2013

201305_R1ProgressRep

June 2013

201306_R1ProgressRep

July 2013

201307_R1ProgressRep

August 2013

201308_R1ProgressRep

September 2013

201309_R1ProgressRep


PCR Temps March-Aug-2013.png

October 2013

201310_R1ProgressRep

November 2013

201311_R1ProgressRep

December 2013

201312_R1ProgressRep

January 2014

201401_R1ProgressRep


JLab shipment

Plan: Lift chambers + Pallets out of Physics and carry them to ISU's loading dock using a fork lift on Wednesday January 8 when ISU is on Thanksgiving break. The chambers will be stored inside a heated building over thanksgiving break and be ready for pickup.

Rick at Partner Steel needs to be called in December with a final date

A fork lift reservation needs to be confirmed with Wade in December.


CLAS12_R1

February 2014

201402_R1ProgressRep

March 2014

201403_R1ProgressRep