CLAS12 R1 Progress Reports
The Drift Chamber Wiki at JLab
Clean room Prep
Clean room Construction 2011
Jlab Shipment 8/8/2011
Jlab Stringing Prep
Install fixtures
8/9/11
Installed the crane
Brought down the platforms
Bring down the scissor lifts
8/17/11
Install A-Frame for mounting DCs
Mounting Sector 1 DC
Changing Room
8/23/11
Finished installing the changing room. The changing room is used to put on clean room apparel prior to entering the clean room. A HEPA filter is placed on top of the room and set to high in order to blow particles off a person before they enter the clean room.
We still need to install a hard door between the changing room and the clean room.
Clean Room 8/23/11
September 2011
October 2011
10/7/11
63 wires were strung today.
14:00 on the temperature graph is 8:00 AM.
10/10/11
In an effort to increase the speed and accuracy of the tensioner, I (Larry) made this little do-hicky:
This is a Fiskars 6"x24" Acrylic Ruler with black foam board glued to the backside. I used a heat gun to bend it 90°. I was just trying this out to see how well it works. If my stringers like it, I will remove the foam board and paint the backside black.
The lines on the acrylic ruler allow a stringer to more easily position the wire perpendicular to the end plate when adjusting the pulley used for hanging weights.
The glossy finish might pose a problem, but we will give it a try and see how it works out.
Temperatures this afternoon climbed up to 71.7°. This does not show up on the 5 minute average, so here is the 1 minute average.
Temperature sensitivity (%Delta;t) was changed to ±1° at around 12:45 PM. Will continue to monitor this.
Changing the sensitivity caused our average to drop about 0.5° but the amplitude of our fluctuations decreased. The minimum is lower than I would like, so the sensitivity is being changed back to ±2° at 3:20 PM.
The HVAC filters showed up this afternoon, so this is being replaced. I will continue to monitor temperatures tomorrow. If temperatures climb back up to 72° again, I will change our sensitivity back down to ±1° as well as change our temperature setpoint to 69° (up 1°) in an attempt to keep our average closer to 70°.
63 field wires were strung today.
10/11/11
It appears that changing our HVAC filter dropped our average temperature to 69° with fluctuations of ±1°.
The temperature setpoint is being increased to 69° in an attempt to get our average to 70°. This was done around 9 AM.
This change did not work as hoped for. This 1° change in our setpoint increased our cleanroom average temperature to 71° with fluctuations of ±1°.
There was no stringing done this morning.
The temperature set point was changed back to 68°. The average temperature did not drop back down to 69°, but only dropped down to 70°.
Stringing resumed once temperatures stayed within acceptable levels (~11 AM).
Average temperatures remained right at 70° with ±1° fluctuations the remainder of the day, even with both of us stringing and measuring tensions.
Even with no stringing this morning, Marcie and I still managed to string 63 wires today.
10/12/11
Temperatures look much better this morning. Screenshots were taken at 8:45 AM.
It was just me (Larry) stringing today, but I still managed to string 42 wires.
My do-hicky seems to be working out well (see pics at 10/10/11). It seems to speed up tensioning wires. Marcie likes it as well.
10/13/11
63 wires were strung today.
10/14/11
98 wires were strung today.
After measuring tension for an extended period of time, temperatures started to climb past 71°. They still remained under 72°.
While working as the bottom stringer, I noticed my cleanroom cap making contact with the crimp pins near the nose. This prompted me to find a way to prevent any further contact with the crimp pins. My solution was to cut out a piece of my black foam board and attaching it to the rails of the endplate. The crimp pins did not appear to protrude past the endplate rails and the double sided tape used to keep the board attached to the rails are about 2mm thick, so there shouldn't be any contact with the board and the crimp pins. I also verified this visually.
This was just a simple, quick, and temporary way to solve this problem. A more permanent solution will be made once I am afforded the time. Maybe a thin sheet of aluminum with 1/8" spacers.
10/17/11
We had a late start today. Only managed to do 63 wires today.
10/18/11
Slow day today. Only 35 wires done today.
The magnet was on for an extended period of time and we saw an increase in our temperatures again. I will need to increase the frequency of our tension measurements in an attempt to avoid keeping the magnet on for too long.
Here is a screenshot of our scope during tension measurements:
10/19/11
70 wires were strung today.
We sorted through our stringer applicants (total 23 applicants) and are scheduling interviews over the next 2 days.
10/20/11
56 wires were strung today.
10/21/11
63 wires were strung today.
10/22/11
Measured all tensions from Friday, including the weekly trend test.
10/24/11
77 wires were strung today.
10/25/11
84 wires were strung today.
Due to the construction in the adjacent room and the increase in our particle counts, the decision was made to replace all of our pre-filters. The decrease in our particle counts this evening almost caused me to change my mind and not replace the filters, but I decided to continue.
Most of the filters were dirty, but they were not too bad. The old filters were the allergen type filters (1200 rating?) and they were replaced with 600 rating filters. We'll see how our particle counts and temperatures are affected.
Filter replacement was done after all work for the day was finished.
10/26/11
Since we were short a stringer (Marcie was sick), Mallory and I spent the morning looking for crossed wires, fixing them and checking tensions. With the small amount of time I had left, I strung 14 wires.