CLAS12 R1 Progress Reports
The Drift Chamber Wiki at JLab
Clean room Prep
Clean room Construction 2011
Jlab Shipment 8/8/2011
Jlab Stringing Prep
Install fixtures
8/9/11
Installed the crane
Brought down the platforms
Bring down the scissor lifts
8/17/11
Install A-Frame for mounting DCs
Mounting Sector 1 DC
Changing Room
8/23/11
Finished installing the changing room. The changing room is used to put on clean room apparel prior to entering the clean room. A HEPA filter is placed on top of the room and set to high in order to blow particles off a person before they enter the clean room.
We still need to install a hard door between the changing room and the clean room.
Clean Room 8/23/11
9/22/11
The doors into the clean room have been sealed by temporary walls for the renovation project which will start in the room next door. Below is a picture of the wall which has sheet rock on top of a plastic cover surrounding metal studs. The wall has been calked on the outside to prevent dust from coming through.
Also note that the HVAC temperature setpoint was changed to 70° F around noon.
9/23/11
2 - 480 V outlets have been installed.
Cleanroom fans were turned on this afternoon around 2:30 PM.
Stringing Begins 9/26/11
HVAC temperature setting was dropped to 67° from 68° and the Δt was changed from ±2° to ±4° at around 1 PM.