CLAS12 R1 Progress Reports

From New IAC Wiki
Jump to navigation Jump to search

The Drift Chamber Wiki at JLab

Clean room Prep

CleanRoomPrep2009-2011

Clean room Construction 2011

CleanRoomConstruction2011

Jlab Shipment 8/8/2011

JLabShipment08082011

Jlab Stringing Prep

Install fixtures

8/9/11

Installed the crane

1CLAS12DC Crane 08092011.jpg2CLAS12DC Crane 08092011.jpg


Brought down the platforms

1CLAS12DC Platform 08092011.jpg2CLAS12DC Platform 08092011.jpg


Bring down the scissor lifts

2CLAS12DC scissorLift 08092011.jpg

8/17/11

Install A-Frame for mounting DCs

1CLAS12DC Aframe1 08092011.jpg2CLAS12DC Aframe1 08092011.jpg

Mounting Sector 1 DC

1CLAS12DC MountDCS1 08092011.jpg2CLAS12DC MountDCS1 08092011.jpg3CLAS12DC MountDCS1 08092011.jpg4CLAS12DC MountDCS1 08092011.jpg

Changing Room

8/23/11

Finished installing the changing room. The changing room is used to put on clean room apparel prior to entering the clean room. A HEPA filter is placed on top of the room and set to high in order to blow particles off a person before they enter the clean room.

2CLAS12DC ChanginRoom 08232011.jpg

We still need to install a hard door between the changing room and the clean room.

Clean Room 8/23/11

1CLAS12DC CleanRoom 08232011.jpg2CLAS12DC CleanRoom 08232011.jpg


9/22/11

The doors into the clean room have been sealed by temporary walls for the renovation project which will start in the room next door. Below is a picture of the wall which has sheet rock on top of a plastic cover surrounding metal studs. The wall has been calked on the outside to prevent dust from coming through.


09222011 CLAS12DC CleanRoom.jpg


CLAS12_R1