Difference between revisions of "CLAS12 R1 Progress Reports"
Jump to navigation
Jump to search
Line 56: | Line 56: | ||
[[File:1CLAS12DC_CleanRoom_08232011.jpg| 200 px]][[File:2CLAS12DC_CleanRoom_08232011.jpg| 200 px]] | [[File:1CLAS12DC_CleanRoom_08232011.jpg| 200 px]][[File:2CLAS12DC_CleanRoom_08232011.jpg| 200 px]] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
[[ CLAS12_R1]] | [[ CLAS12_R1]] |
Revision as of 14:41, 22 September 2011
The Drift Chamber Wiki at JLab
Clean room Prep
Clean room Construction 2011
Jlab Shipment 8/8/2011
Jlab Stringing Prep
Install fixtures
8/9/11
Installed the crane
Brought down the platforms
Bring down the scissor lifts
8/17/11
Install A-Frame for mounting DCs
Mounting Sector 1 DC
Changing Room
8/23/11
Finished installing the changing room. The changing room is used to put on clean room apparel prior to entering the clean room. A HEPA filter is placed on top of the room and set to high in order to blow particles off a person before they enter the clean room.
We still need to install a hard door between the changing room and the clean room.
Clean Room 8/23/11