== 9/22/11==
The doors into the clean room have been sealed by temporary walls for the renovation project which will start in the room next door.  Below is a picture of the wall which has sheet rock on top of a plastic cover surrounding metal studs.  The wall has been calked on the outside to prevent dust from coming through.
[[File:09222011_CLAS12DC_CleanRoom.jpg | 200 px]]




[[ CLAS12_R1]]
[[ CLAS12_R1]]

Revision as of 14:45, 22 September 2011

The Drift Chamber Wiki at JLab

Clean room Prep

CleanRoomPrep2009-2011

Clean room Construction 2011

CleanRoomConstruction2011

Jlab Shipment 8/8/2011

JLabShipment08082011

Jlab Stringing Prep

Install fixtures

8/9/11

Installed the crane


Brought down the platforms


Bring down the scissor lifts

8/17/11

Install A-Frame for mounting DCs

Mounting Sector 1 DC

Changing Room

8/23/11

Finished installing the changing room. The changing room is used to put on clean room apparel prior to entering the clean room. A HEPA filter is placed on top of the room and set to high in order to blow particles off a person before they enter the clean room.

We still need to install a hard door between the changing room and the clean room.

Clean Room 8/23/11


9/22/11

The doors into the clean room have been sealed by temporary walls for the renovation project which will start in the room next door. Below is a picture of the wall which has sheet rock on top of a plastic cover surrounding metal studs. The wall has been calked on the outside to prevent dust from coming through.