Goals

measure the Beam spot size on target

Measure the Transmission

Measure Positrons produced

Runs

Setup

Detector2 (NaI-2 , S/N 60002-8292-I) is at beam left. It needs 1080 V. IAC_NaI_Detectors#Det2

Detector3 is at beam right. It needs 1060 V. IAC_NaI_Detectors#Det3

(When taking down the experiment It was observed that NaI-1, S/N 60002-8454-I was on the Beam right location).
NaI-3 was replaced with NaI-1 after run#3663. 

HRRL_Positrons_Jul_2012_Runs_Setup

T1 converter Target spec

0.04 inch = 1.016 mm: File:CHIPs T1 TungstenTargetMatCert 1mm.pdf


In the second week we changed T2 to the same target as T1.

HRRL_Positrons_Jul_2012_Runs_Setup#Targets

Shieldings

hrrl_pos_jul2012_shieldings

What will I do if I run again

Improvements_HRRL_Positron_Runs_July_2012

Links

Dipole mapping: [[1]]