Line 26: | Line 26: | ||
Ship back equipment: ship one of the A-Frames and associated equipment for stringing one chamber. | Ship back equipment: ship one of the A-Frames and associated equipment for stringing one chamber. | ||
+ | =11/15/13= | ||
+ | S3 stringing is done. | ||
+ | David - Preparing for potting on S3 - remove magnet, stringing machine and rail, setup potting equipment & start on top side of S3. | ||
+ | |||
+ | Haitham - Trace, cut, and tape on dust covers for S5's HVB's. | ||
+ | |||
+ | Derrick - 1 palette mostly constructed, should have a second done by the end of this weekend. Will need 3 ready before 11/26. | ||
[[CLAS12_R1_Progress_Reports]] | [[CLAS12_R1_Progress_Reports]] |
Latest revision as of 16:49, 15 November 2013
11/04/13
S2: 17 wires; 6 field, 11 sense
SL1 - 6 field, 9 sense
SL2 - 2 sense (done)
S3: 16 wires; 14 field, 2 sense
SL2 - 4 field, 1 sense
Total wires left to replace between both chambers: 16
S2 determine if we are ready to rotate (will continue working on S2 in December) S3 ready to align SL2
Prepare to Ship 2 chambers
S6 is boxed up and ready to go on a pallet
S5: Pictures taken on most sense wires, SL1 has almost 3 Ua of current draw (need to debug), need to box it up unless we ship S1.
Ship back equipment: ship one of the A-Frames and associated equipment for stringing one chamber.
11/15/13
S3 stringing is done.
David - Preparing for potting on S3 - remove magnet, stringing machine and rail, setup potting equipment & start on top side of S3.
Haitham - Trace, cut, and tape on dust covers for S5's HVB's.
Derrick - 1 palette mostly constructed, should have a second done by the end of this weekend. Will need 3 ready before 11/26.