AW CLAS12R1
11/1/2013
- Goals
- Confirm signals on all of Sector 5's sense wires
- Finish HV burnin: S:F:G = 1500:-750:536 and the current draw is less than 1 uA CLAS12_R1_S5_QA
- After the above is completed, stop gas flow, Install dust covers, prepare for shipping
- Test TDC integrity using DAQ and S1
- Available times
- Monday 9-5
- T,Th 9-3
- W,F 12-5
Weekly progress meeting at 10 am Mondays