Beam Line Budget
3 week lead time on flanges
goal will be to run on Dec 2 or Dec 9.
Without 6 cross
| Cost ($) | 
Description
 | 
| 318 | 
Bellows
 | 
| 158 | 
Hardware (nuts & bolts)
 | 
| 290 | 
5 rotatable flanges
 | 
| 335 | 
non-rotatable flanges
 | 
 | 
7' + 6' + 3' SS pipe lengths
 | 
| 250 | 
turning pipe on lathe
 | 
| 2400 | 
2 days of labor building beam line components and 1 day installation
 | 
With 6 cross
| Cost ($) | 
Description
 | 
| 0 | 
5 mil  exit window
 | 
| 0 | 
338 cube for 6 cross (2" pipe max diameter)
 | 
| 221 | 
glass exit  window for beam view screen
 | 
| 232 | 
4 rotatable flanges
 | 
| 268 | 
4 non-rotatable flanges
 | 
 | 
6 " SS beam pipe
 | 
| 800 | 
1 day of labor building 6 way cross
 | 
Positrons_Using_40Mev_Linac#10.2F14.2F13