201310 R1ProgressRep

From New IAC Wiki
Revision as of 16:13, 18 October 2013 by Foretony (talk | contribs) (Created page with " =10/18/2013= Current total loose wires we need to fix (try pulling on the pin) on both chambers combined (our only uncertainty in how many additional replacements there could b…")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

10/18/2013

Current total loose wires we need to fix (try pulling on the pin) on both chambers combined (our only uncertainty in how many additional replacements there could be):

6

Current total known replacement wires that need to be done:

S2: 17 wires; 6 field, 11 sense SL1 - 6 field, 9 sense SL2 - 2 sense

S3: 16 wires; 14 field, 2 sense SL1 - 10 field, 1 sense SL2 - 4 field, 1 sense

Total wires left to replace between both chambers: 33

S2 is aligned for stringing on SL2 - 2 wires left to string on this superlayer before we need to re-align. S3 is aligned for stringing on SL1 - 11 wires left to string on this superlayer before we need to re-align.


CLAS12_R1_Progress_Reports