201308 R1ProgressRep

From New IAC Wiki
Jump to navigation Jump to search

7/24/13

Dion: String S2 with David ; left at 12:30

David: String S2 with Dion ; left at 12:30

Debbie: took a position at ON semiconductor

Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5


S6 Testing and Performance Summary


Carlos: working full time on NSF grant now

S2 : stringing will finish this week

S3: stringing finished


CLAS12_R1_Progress_Reports