2/4/13
Goals:
- number feedthrough on S3
- install S2 onto A-frame
- make protective covers for S5
Installed S2 onto A-Frame along with stringing rail and Magnet.
Half of the feed-throughs were numbered
Finished top cover for S5, crimp pin covers will be worked on tomorrow
2/5/13
Goals:
- Finish numbering feed-throughs on S3
- finish constructing crimp pin covers and window cover
- Install "new" stringing machine on S2
- re-string 5 bent wires from S5
2/6/13
Goal:
- pot S3 wires
2/7/13
Goal:
- remove S5 from A-Frame
- purge inside of S3 with nitrogen to remove particles before moving to clean room
- place S3 on floor of clean room for pre-tensioning
- Level A-frame for S3
2/11/13
Goal:
- remove S5 from clean room
- Level A-frame
- Install S3 pre-tensioners
onto A-Frame in clean room
2/12/13
Goals:
- Finish installing pre-tensioners on S3
- mount S3 onto A-frame
- Clean the Clean room to prepare for stringing (vacuum shavings from hoist, clean all wall surfaces, clean A-Frames and DC strong-backs, lifts, both white tables, ladders, computer keyboard)