CLAS12R1ReadinessReview2011

From New IAC Wiki
Revision as of 15:17, 19 August 2011 by Foretony (talk | contribs)
Jump to navigation Jump to search

File:08182011ISUCleanRoomStatus.ppt

1.) The project managers name and contact info (Phone and e-mail address)

Tony Forest, 208-282-4426, tforest@jlab.org
Dustin McNulty,208-282-4901,mcnudust@isu.edu

2.) A current or updated copy of their QA Plan including any checklists or forms

File:QAPlan.doc

File:QAPlan.pdf

3.) Assembly procedures and non-conformance procedures including interfaces with JLab to resolve problems

Larry Lim is working on assembly procedures.

4.) Any other current or updated documents needed for reference prior to and during the review

R1 Stringing Manual (Updated by Larry Lim)

https://wiki.iac.isu.edu/index.php/CLAS12_R1_Stringing_Manual

5.) A project org chart

R1OrgChartCLAS12.png

6.) Floor plan layout for staging materials, assembly, production, testing, packaging, and shipping

Bob Millers Clean room layout

File:06012011Rmiller CleanRoomLayout.doc

Design Drawings.

http://www.physics.isu.edu/~tforest/R1_Fixtures/

Basement Floor Plan for staging and storage

File:BasementRenovationDrawing 6-16-10.pdf

7.) Directions to the location where we intend to meet with the ISU project manager and his/her team

8.) Pertinent training records for technicians and staff expected to be working on the project

Record of interviewee's wire stringing test results.

2nd stringing team paired with experiences team to improved information transfer.

Scissor lift manual.

HV training.

Suspect/counterfeit items. DOE has training material for us to review.

9.) List of calibrated equipment and records of current calibrations if applicable

Device
Temp purchased in 2009
Kanomax Particle Counter Purchased 8/2011


10.) Plan of how students will be used, what functions they will perform, and who will be supervising the project/operations

Students are not expected to be used in this project.

Action Items

ISU items

1.) Take control of HVAC. Agreement with M & O to have temperature set to 70 F. Establish an on call technician for repairing the HVAC at a moments notice.

2.) Name the chambers (don't put sector ID in the names)

3.) Protection cover for chamber when moving onto and off of spit. Protect it from the chain hoist chains.

4.) Black backdrop and extra lighting in stringing area.

5.) Continue to look for problems with box construction.

6.) Testing procedure (plateau curve at some point)

7.) Order the power supply below from CAEN product code WN1471X05AAC (N1471 - 4 Ch NIM Programmable HV Power Supply (±5.5kV, 300µA, 5nA res.)

8.) Monthly progress report spreadsheet. Check with Steve Christo for Activity IDs and if Larry's Template is still good.

9.) Spool wire and crimp pin in data base. Record which spool and crimp pin was used for which detector. A flag indicating that the wire was inspected. Send Steve e-mail acknowledging receipt of wire and crimp pins.

10.) Meticulously clean up wire clippings. Review how sense wire is used

11.) Ask Larry what Tom's duties are as our Technician will be doing his tasks.

12.) Ask Manufacturer for calibration procedure and how often to recalibrate.

13.) Siren light for magnet

14.) Visual feedthrough inspection

15.) Don't cut curtains

16.) Testing sense wires, scope signal type training

17.) HVAC, 30 x 30 filter supply, thermostat in middle clean room

18.) Larry Lim writes weekly progress descriptions in the wiki.

19.) Dial indicator measurement of endplate deflection before and after stringing. Several rails attached to strongback with location holes and can reproduce mounting the dial indicator.

JLab items

1.) Shipping procedure for return (temp and pressure controls)

2.) Pre-Tension release procedure from George (may already be in the manual)

3.) HV conditioning procedures for initial startup

4.) Exposed apoxy, probably do nothing

5.) What should the temperature alarm threshold be? +/- 2 F or 5???

Group action items

1.) Measure temp dependence of wire tension

2.) Stringing checklist ONE manual

3.) MySQL will be used. Make final data base decisions on what information is in it; Tension, batch, shipping. wire received, wire status, chamber using wire.

4.) Another stringing manual review

5.) Daily tension re-measure procedure.


CLAS12_R1#Readiness_Review