HRRL Move 2010
Timeline
Start Date | Finish Date | Task |
10/01/10 | 11/01/10 | Move the HRRL and construct new beamline |
11/01/10 | 11/15/10 | Measure Radiation Field and Prepare for Hunt Run |
11/15/10 | 12/17/10 | Hunt Beam Time (3 MeV, 300 Hz, multiple pulsing) |
01/03/10 | 01/14/10 | Prepare for high current emmittance measurements |
01/18/10 | 01/21/10 | high current emmittance measurements (10 MeV, 50 ns pulse width, variable rep rate and current) |
Tasks
Design and build required infrastructure
Beam line CAD
The location of all magnets is provided by Yujong Kim.
Kevin Folkman will layout the CAD drawings
Accelerator Wall Mount
A mounting system needs to be designed for the HRRL which will be used for its new position. It is unclear if we can reuse the current stands. We will want a way to add lead sheets around the HRRL and the location of the Tungsten converter target which is after the first 3 quads and labeled (PT) in the drawings.
Stands
Chad has built one stand to hold 3 Quads. We will need 3 more stands built to hold quad triples and 2 stands to hold the "Kiwi" dipoles.
FC cooling
We need to solder cooling lines around the FC.
Move the HRRL
10/1/10
Install HRRL cavity mounting system
10/4-6/10
Disassemble beam line and move HRRL cavity to new location
10/7-14/10
- Alignment
A lot of time is being allocated to align the accelerator
Khalid and Sadiq will work on leveling the accelerator and mount alignment targets on the wall..
parts List
- 6 cross which connects the JLab flags, 2 ports for beam, 1 port for JLab flag, 1 port for optical window , 1 port for ion pump, remaining port blanked.
- a gun valve which comes out at 90 degrees to the beam line to use of less space
- Danfysik water cooled Slit model 563
Design preference
Thin aluminum target for OTR right after 3 quads place at exit to Linac