8/5/13

Dion: String S2 with David ; left at 12:30

David: String S2 with Dion ; left at 12:30

Debbie: took a position at ON semiconductor

Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5


S6 Testing and Performance Summary


Carlos: working full time on NSF grant now

S2 : stringing will finish this week

S3: stringing finished

8/6/13

Dion: String S2 with David ;

David: String S2 with Dion ;


Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5

S2 : stringing will finish this week


8/7/13

Dion: String S2 with David ;

David: String S2 with Dion ; arrived around 9am


Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5

S2 : stringing will finish this week


8/8/13

Dion: solder HV boards & Measure Tensions

David: solder HV boards & Measure Tensions


Haitham: off today

S2 : finished stringing yesterday

Tasks remaining:

  1. Measure all Field and Sense wire tensions prior to potting
  2. pot S2 & S3
  3. install Windows on S2 & S3
  4. install HVBs & STBs onto S2 & S3
  5. burn in S2 & S3
  6. finish Q&A on all chambers

8/22/13

Finished testing all Field and Sense wires in S3 last week

Almost finished testing S2 today.

David Coneff is managing two student workers and plans to finish the above remaining tasks before Jan 2014 as a part time worker. Debbie Mosbrucker and Dion Almond are working at ON semi-conductor now.