7/04/13

Clean room HVAC Low temperature alarm went off. Charts show that at 4am the temperature started dropping from 68 to 66 at noon.

Changed set point from 67 to 68.

The temperature monitor indicates that the temperatures went back to 70 degrees by 8pm.

Temp 07052013.png

crimpers are gapped at 0.03" (0.765 mm) every hour

7/08/13

Dion: String S3 with Debbie, taking afternoon off

Haitham: String S2 with David

David: String S2 with Haitham, install octopus on S5 SL2 and start HV burn in

Debbie: String S3 with Dion

Carlos: wire tension measurments, work on analyzing data to determine efficiency


S2: on Sense wire row 109

S3: on Sense wire row 163


S5, guard, crimped part was 0.043", uncrimped pin 0.065 ".


7/09/13

Dion: Solder HV boards & look for S5SL1 signals, String S3 with David in the afternoon

Haitham: String S2 with David

David: String S2 with Haitham in the morning S3 with Dion in the afternoon

Debbie: day off

Carlos: wire tension measurements, work on analyzing data to determine efficiency


S2: on Sense wire row 130

S3: on Sense wire row 182


other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,


7/10/13

Dion: String S3 with David

Haitham: String S2 with Debbie

David: String S2 with Dion

Debbie: String S2 with Haitham

Carlos: wire tension measurements, work on analyzing data to determine efficiency


S2: on Sense wire row

S3: on Sense wire row


other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,

7/15/13

Dion: String S2 with David

David: String S2 with Dion

Debbie: String S3

Haitham: HV burn in S5 and test signals

Carlos: wire tension measurements, work on analyzing data to determine efficiency


S2: on Sense wire row 184

S3: on Sense wire row 2 (on the last super layer)


other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,

7/16/13

Dion: String S2 with David , took afternoon off

David: String S2 with Dion

Debbie: String S3

Haitham: HV burn in S5 and test signals

Carlos: wire tension measurements, work on analyzing data to determine efficiency


other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,

7/17/13

Dion: String S2 with David

David: String S2 with Dion

Debbie: started String S3 at 9am

Haitham: HV burn in S5 and test signals

Carlos: wire tension measurements, work on analyzing data to determine efficiency


S2: on Sense wire row 3 SL1 (Last superlayer)

S3: on Sense wire row 38

other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,

7/18/13

Dion: String S2 with David

David: String S2 with Dion

Debbie: started String S3

Haitham: HV burn in S5 and test signals

Carlos: wire tension measurements, work on analyzing data to determine efficiency


S2: on Sense wire row 16

S3: on Sense wire row 58

other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,