IAC LeadFlourideCherenkovCrystalTests 5-09
Jump to navigation
Jump to search
http://clasweb.jlab.org/wiki/index.php/Hall_A_IAC_Tests
Previous Tests: IAC_LeadFlourideCherenkovCrystalTests
Run Plan
Summary
{| Task | Time Budget | |
| (mm) | plastic | metal |
| Beam setup | 0.5 days | |
| Testing 20 new blocks | 2.5 days | |
| Silicon test | 1.0 day | |
| Bleaching/Re-irradiation test | 0.5-1 day | |
| Testing old blocks | 12 blocks/day |