IAC LeadFlourideCherenkovCrystalTests 5-09
Jump to navigation
Jump to search
http://clasweb.jlab.org/wiki/index.php/Hall_A_IAC_Tests
Previous Tests: IAC_LeadFlourideCherenkovCrystalTests
Run Plan
Summary
{ |- Beam setup | 0.5 days Testing 20 new blocks & 2.5 days\\ Silicon test & 1.0 day \\ Bleaching/Re-irradiation test & 0.5-1 day\\ Testing old blocks & 12 blocks/day\\