201204 R1ProgressRep
4/2/2012
Started stringing SL1. Strung 48 guard wires, now on row 45 SL1.
R1 S1 sense wire signals
4/3/2012
Column is high number
Continued stringing SL1 guard wires. Strung 35 wires, now on row 80.
Soldered more stringing chains.
4/4/12
HVB-2
Strung 75 Guard wires (now on row 156).
4/5/12
Mounted Chamber 5 on A-Frame. Strung 44 guard wires through row 200.
4/6/12
Mounted magnet and stringing rail on Chamber 5. Strung 33 guard wires finishing guards on Chamber 6.
4/9/12
Visual inspection of Ch 6 Guard wires complete. Ready to start stringing Field wires tomorrow.
Mounted stringing arm and stringing machine on Ch 5. Ch 5 ready for stringing.
4/10/12
Aligned Ch 6 for SL2 stringing. Strung 36 Field wires through row 7.
4/11/12
Strung 63 Field wires through row 17 SL2.
4/12/12
Strung 21 Field wires through row 21 SL2. Reattached clean room wall and shifted it to allow more room. Before and after pictures to be uploaded soon.
4/13/12
Strung 70 Field wires through row 31 SL2.
4/16/12
Shopping List:
power strip
magnetic tray for tools (9.5"x5.5")
small table with wheels (LxWxH = 24"x20"x36")
round metal trash canister (DxH = 5.5"x6")
2 trash canisters for lifts (diameter less than 6")
3 alcohol refill bottles
2 metal crimp pin bowls for lifts (diameter less than 6")
step ladder for bottom stringer
medium plastic storage bin
chain bag for hoist
Strung 84 Field wires in SL2. On row 44 now.
4/17/12
Strung 91 Field wires.
It was brought to our attention this afternoon, by Dr. McNulty, that we need to keep a separate work log to record who is stringing, clean-room temperatures, etc. We were tasked with creation of a new Excel file for this purpose and will transfer our existing records to this file tomorrow.
4/18/12
Strung 98 Field wires.
Reattached part of the clean room wall that had fallen.