Jan 22, 2012 Readiness Review


Currently scheduled Injector recovery on October 22

Positrons May be November 4 & 5


Currently max energy is 7.8 MeV.


Choosing 6.3 MeV incident electron energy because that is the most stable.

[math]\sigma[/math] = 0.5 mm on the Tungsten target (T1)


June Racks installed and cables pulled to tunnel
August 2011 vacuum pumps ready, Compton Polarimeter Table installed
September 2011 Beam Line installed
October 2011 Finish Work in Injector area for PePPO
October 17-19, 2011 Swing shift hot checkout
October 29-Nov 1 2011 Owl shift PePPo tuning (Probably install Annihilation counter here)
Nov 11-16 2011 Day shift PePPo running