HRRL Move 2010
Timeline
Start Date | Finish Date | Task |
10/01/10 | 11/01/10 | Move the HRRL and construct new beamline |
11/01/10 | 11/15/10 | Measure Radiation Field and Prepare for Hunt Run |
11/15/10 | 12/17/10 | Hunt Beam Time (3 MeV, 300 Hz, multiple pulsing) |
01/03/10 | 01/14/10 | Prepare for high current emmittance measurements |
01/18/10 | 01/21/10 | high current emmittance measurements (10 MeV, 50 ns pulse width, variable rep rate and current) |
Tasks
Design and build required infrastructure
Beam line CAD
The location of all magnets is provided by Yujong Kim.
Kevin Folkman will layout the CAD drawings
Accelerator Wall Mount
A mounting system needs to be designed for the HRRL which will be used for its new position. It is unclear if we can reuse the current stands. We will want a way to add lead sheets around the HRRL and the location of the Tungsten converter target which is after the first 3 quads and labeled (PT) in the drawings.
Stands
Chad has built one stand to hold 3 Quads. We will need 3 more stands built to hold quad triples and 2 stands to hold the "Kiwi" dipoles.
FC cooling
We need to solder cooling lines around the FC.
Move the HRRL
10/1/10
Install HRRL cavity mounting system
10/4-6/10
Disassemble beam line and move HRRL cavity to new location
10/7-14/10
- Alignment
A lot of time is being allocated to align the accelerator
Khalid, Sadiq, and an IAC theodolite operator will work on leveling the accelerator and mount alignment targets on the wall..
1.) Alignment:
a.) spare gun
b.) laser with targets mounted on wall.
Design preference
Thin aluminum target for OTR right after 3 quads place at exit to Linac