HRRL Move 2010

From New IAC Wiki
Revision as of 14:56, 2 September 2010 by Oborn (talk | contribs) (→‎Timeline)
Jump to navigation Jump to search

Timeline

Start Date Finish Date Task
10/1/10 11/1/10 Move the HRRL and construct new beamline
11/1/10 11/15/10 Measure Radiation Field and Prepare for Hunt Run
11/15/10 12/17/10 Hunt Beam Time (3 MeV, 300 Hz, multiple pulsing)
1/3/10 1/14/10 Prepare for high current emmittance measurements
1/18/10 1/21/10 high current emmittance measurements (10 MeV, 50 ns pulse width, variable rep rate and current)

Tasks

1.) Alignment: a.) spare gun b.) laser with targets mounted on wall.


Design preference

Thin aluminum target for OTR right after 3 quads place at exit to Linac