Beam Line Budget

3 week lead time on flanges

goal will be to run on Dec 2 or Dec 9.

Without 6 cross

Cost ($) Description
318 Bellows
158 Hardware (nuts & bolts)
290 5 rotatable flanges
335 non-rotatable flanges
7' + 6' + 3' SS pipe lengths
250 turning pipe on lathe
2400 2 days of labor building beam line components and 1 day installation

With 6 cross

Cost ($) Description
0 5 mil exit window
221 glass exit window for beam view screen
232 4 rotatable flanges
268 4 non-rotatable flanges
6 " SS beam pipe
800 1 day of labor building 6 way cross