Difference between revisions of "201308 R1ProgressRep"
(→8/6/13) |
(→8/7/13) |
||
Line 43: | Line 43: | ||
+ | |||
+ | =8/8/13= | ||
+ | |||
+ | Dion: solder HV boards & Measure Tensions | ||
+ | |||
+ | David: solder HV boards & Measure Tensions | ||
+ | |||
+ | |||
+ | Haitham: off today | ||
+ | |||
+ | S2 : finished stringing yesterday | ||
+ | |||
+ | Tasks remaining: | ||
+ | |||
+ | #Measure all Field and Sense wire tensions prior to potting | ||
+ | # pot S2 & S3 | ||
+ | #install Windows on S2 & S3 | ||
+ | #install HVBs & STBs onto S2 & S3 | ||
+ | #burn in S2 & S3 | ||
+ | #finish Q&A on all chambers | ||
[[CLAS12_R1_Progress_Reports]] | [[CLAS12_R1_Progress_Reports]] |
Revision as of 16:36, 8 August 2013
8/5/13
Dion: String S2 with David ; left at 12:30
David: String S2 with Dion ; left at 12:30
Debbie: took a position at ON semiconductor
Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5
S6 Testing and Performance Summary
Carlos: working full time on NSF grant now
S2 : stringing will finish this week
S3: stringing finished
8/6/13
Dion: String S2 with David ;
David: String S2 with Dion ;
Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5
S2 : stringing will finish this week
8/7/13
Dion: String S2 with David ;
David: String S2 with Dion ; arrived around 9am
Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5
S2 : stringing will finish this week
8/8/13
Dion: solder HV boards & Measure Tensions
David: solder HV boards & Measure Tensions
Haitham: off today
S2 : finished stringing yesterday
Tasks remaining:
- Measure all Field and Sense wire tensions prior to potting
- pot S2 & S3
- install Windows on S2 & S3
- install HVBs & STBs onto S2 & S3
- burn in S2 & S3
- finish Q&A on all chambers