David: String S2 with Dion ;  
 
David: String S2 with Dion ;  
 +
 +
 +
Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5
 +
 +
S2 : stringing will finish this week
 +
 +
 +
=8/7/13=
 +
 +
Dion: String S2  with David ;
 +
 +
David: String S2 with Dion ; arrived around 9am
  
  

Revision as of 20:53, 7 August 2013

8/5/13

Dion: String S2 with David ; left at 12:30

David: String S2 with Dion ; left at 12:30

Debbie: took a position at ON semiconductor

Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5


S6 Testing and Performance Summary


Carlos: working full time on NSF grant now

S2 : stringing will finish this week

S3: stringing finished

8/6/13

Dion: String S2 with David ;

David: String S2 with Dion ;


Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5

S2 : stringing will finish this week


8/7/13

Dion: String S2 with David ;

David: String S2 with Dion ; arrived around 9am


Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5

S2 : stringing will finish this week