=3/19/13=
 
=3/19/13=
  
Dion: String S2 Field with David in the morning then switch to S3 after Debbie arrives
+
Dion: String S3 Field with David  
  
David: String S2 with Dion then S3 Field
+
David: String S3 with Dion  
  
Debbie: String S2 after arriving late
+
Debbie: sick day
 +
Haitham: Look for signals on S6 then String Field S2 when Debbie arrives
 +
 
 +
Carlos: Wire tension measurements & ADB crate install
 +
 
 +
=3/20/13=
 +
 
 +
Dion: String S2 Field with David
 +
 
 +
David: String S2 with Dion
 +
 
 +
Debbie: sick day
 
Haitham: Look for signals on S6 then String Field S2 when Debbie arrives
 
Haitham: Look for signals on S6 then String Field S2 when Debbie arrives
  

Revision as of 20:24, 20 March 2013

3/4/13

Dion: String S3 with David

David: Stringing S3 Guard

Debbie: String S2 in the morning, HV burn in S6 in the afternoon

Haitham: String Guard on S2

Carlo: HV burn in & signal search S6


Progress: A super layer of guard wires has been strung on both S2 & S3. Should be finished with Guard wires by next week

3/5/13

Dion: String S3 with David

David: Stringing S3 Guard

Debbie: String S2 in the morning, HV burn in S6 SL2-HVB6 in the afternoon

Haitham: String Guard on S2

Carlo: HV burn in SL2-HVB6

3/7/13

Signals observed on all channels of S2 SL2 HVB5.

3/11/13

Dion: String S3 Field with David

David: Stringing S3 Field

Debbie: String S2 in the morning, HV burn in S6 SL2-HVB5 in the afternoon

Haitham: String Field S2

Carlo: HV burn in SL2-HVB5

3/18/13

Dion: String S3 Field with David

David: Stringing S3 Field

Debbie: String S2 in the morning, Look for signals on STB5

Haitham: String Field S2

Carlos: Wire tension measurements & ADB crate checkout

3/19/13

Dion: String S3 Field with David

David: Stringing S3 Field

Debbie: String S2 in the morning, Debbie needs time off after lunch

Haitham: String Field S2

Carlos: Wire tension measurements & ADB crate install

3/19/13

Dion: String S3 Field with David

David: String S3 with Dion

Debbie: sick day Haitham: Look for signals on S6 then String Field S2 when Debbie arrives

Carlos: Wire tension measurements & ADB crate install

3/20/13

Dion: String S2 Field with David

David: String S2 with Dion

Debbie: sick day Haitham: Look for signals on S6 then String Field S2 when Debbie arrives

Carlos: Wire tension measurements & ADB crate install