PePPO 2012Run: Difference between revisions
Jump to navigation
Jump to search
| Line 4: | Line 4: | ||
Positrons may be In May | Positrons may be In May | ||
The main electron beam current needs to be limited to 10 nA. | The main electron beam current needs to be limited to 10 nA using a beam line cavity. | ||
Currently max energy is 7.8 MeV. | Currently max energy is 7.8 MeV. | ||
Revision as of 16:11, 23 November 2011
Run Configuration
Positrons may be In May
The main electron beam current needs to be limited to 10 nA using a beam line cavity.
Currently max energy is 7.8 MeV.
Choosing 6.3 MeV incident electron energy because that is the most stable.
[math]\displaystyle{ \sigma }[/math] = 0.5 mm on the Tungsten target (T1)
| Date | Task/Item |
| Jan 22, 2012 | Readiness Review |