Jan 22, 2012  Readiness Review
+
 
  
  
Line 18: Line 18:
 
{| border="1"  |cellpadding="20" cellspacing="0  
 
{| border="1"  |cellpadding="20" cellspacing="0  
 
|-
 
|-
|June || Racks installed and cables pulled to tunnel
+
|Date || Task/Item
|-
 
|August 2011 || vacuum pumps ready, Compton Polarimeter Table installed
 
|-
 
|September 2011 || Beam Line installed
 
|-
 
|October 2011 || Finish Work in Injector area for PePPO
 
|-
 
|October 17-19, 2011 || Swing shift hot checkout
 
|-
 
|October 29-Nov 1 2011 || Owl shift PePPo tuning (Probably install Annihilation counter here)
 
 
|-
 
|-
|Nov 11-16 2011 || Day shift PePPo running
+
|Jan 22, 2012  || Readiness Review
 
|-
 
|-
 
|}
 
|}

Revision as of 15:59, 23 November 2011


Currently scheduled Injector recovery on October 22

Positrons May be November 4 & 5


Currently max energy is 7.8 MeV.


Choosing 6.3 MeV incident electron energy because that is the most stable.

[math]\sigma[/math] = 0.5 mm on the Tungsten target (T1)


Date Task/Item
Jan 22, 2012 Readiness Review


Positrons