Difference between revisions of "PePPO 2011Run"

From New IAC Wiki
Jump to navigation Jump to search
Line 24: Line 24:
 
|-
 
|-
 
|October 2011 || Finish Work in Injector area for PePPO
 
|October 2011 || Finish Work in Injector area for PePPO
|-
 
|October 17-19, 2011 || Swing shift hot checkout
 
 
|-
 
|-
 
|October 17-19, 2011 || Swing shift hot checkout  
 
|October 17-19, 2011 || Swing shift hot checkout  

Revision as of 14:54, 7 September 2011

PePPO run

Currently scheduled Injector recovery on October 22

Positrons May be November 4 & 5


Currently max energy is 7.8 MeV.


Choosing 6.3 MeV incident electron energy because that is the most stable.

[math]\sigma[/math] = 0.5 mm on the Tungsten target (T1)


June Racks installed and cables pulled to tunnel
August 2011 vacuum pumps ready, Compton Polarimeter Table installed
September 2011 Beam Line installed
October 2011 Finish Work in Injector area for PePPO
October 17-19, 2011 Swing shift hot checkout
October 29-Nov 1 2011 Owl shift PePPo tuning
Nov 3-6 2011 Day shift PePPo running

Region 3

Cable length are 75-100 feet long

2 NaI detectors

one has mirror between it and the port window to reflect light to a camera.


See if we can send out one of our actuators to move the mirror in and out.

PePPo NaI Setup.png