Difference between revisions of "CLAS12R1ReadinessReview2011"
Line 69: | Line 69: | ||
Students are not expected to be used in this project. | Students are not expected to be used in this project. | ||
− | + | =Action Items= | |
+ | |||
+ | ==ISU items== | ||
1.) Take control of HVAC. Agreement with M & O to have temperature set to 70 F. Establish an on call technician for repairing the HVAC at a moments notice. | 1.) Take control of HVAC. Agreement with M & O to have temperature set to 70 F. Establish an on call technician for repairing the HVAC at a moments notice. | ||
Line 77: | Line 79: | ||
3.) Protection cover for chamber when moving in. | 3.) Protection cover for chamber when moving in. | ||
− | 4.) Black backdrop and extra lighting in stringing area | + | 4.) Black backdrop and extra lighting in stringing area. |
+ | |||
+ | ==JLab items== | ||
+ | |||
+ | 1.) Shipping procedure for return | ||
+ | |||
+ | 2.) | ||
+ | |||
[[CLAS12_R1#Readiness_Review]] | [[CLAS12_R1#Readiness_Review]] |
Revision as of 16:52, 18 August 2011
1.) The project managers name and contact info (Phone and e-mail address)
- Tony Forest, 208-282-4426, tforest@jlab.org
- Dustin McNulty,208-282-4901,mcnudust@isu.edu
2.) A current or updated copy of their QA Plan including any checklists or forms
3.) Assembly procedures and non-conformance procedures including interfaces with JLab to resolve problems
Larry Lim is working on assembly procedures.
4.) Any other current or updated documents needed for reference prior to and during the review
R1 Stringing Manual (Updated by Larry Lim)
https://wiki.iac.isu.edu/index.php/CLAS12_R1_Stringing_Manual
5.) A project org chart
6.) Floor plan layout for staging materials, assembly, production, testing, packaging, and shipping
Bob Millers Clean room layout
File:06012011Rmiller CleanRoomLayout.doc
Design Drawings.
http://www.physics.isu.edu/~tforest/R1_Fixtures/
Basement Floor Plan for staging and storage
File:BasementRenovationDrawing 6-16-10.pdf
7.) Directions to the location where we intend to meet with the ISU project manager and his/her team
8.) Pertinent training records for technicians and staff expected to be working on the project
Record of interviewee's wire stringing test results.
2nd stringing team paired with experiences team to improved information transfer.
Scissor lift manual.
HV training.
Suspect/counterfeit items. DOE has training material for us to review.
9.) List of calibrated equipment and records of current calibrations if applicable
Device | |
Temp | purchased in 2009 |
Kanomax Particle Counter | Purchased 8/2011 |
10.) Plan of how students will be used, what functions they will perform, and who will be supervising the project/operations
Students are not expected to be used in this project.
Action Items
ISU items
1.) Take control of HVAC. Agreement with M & O to have temperature set to 70 F. Establish an on call technician for repairing the HVAC at a moments notice.
2.) Name the chambers (don't put sector ID in the names)
3.) Protection cover for chamber when moving in.
4.) Black backdrop and extra lighting in stringing area.
JLab items
1.) Shipping procedure for return
2.)