Alignment
Timeline
Completion Date | Task |
4/29/11 | remove HRRL Gun |
5/2/2011 | Install alignment laser |
5/3/2011 | Install rotation and translation stages |
5/9/2011 | Align zero degree beam line |
5/12/2011 | Align 45 degree beam line |
5/13/2011 | Align 90 degree beam line |
Procedure
Equipment
Precision Rotation Stage
Thor Labs 1 arc sec resolution, 5 arc min accuracy, Rotator $2425, APT controller $1600,
Elliot Scientific Manual rotation, 5 arc sec resolution, $600