Difference between revisions of "IAC LeadFlourideCherenkovCrystalTests 5-09"

From New IAC Wiki
Jump to navigation Jump to search
Line 7: Line 7:
 
== Summary==
 
== Summary==
  
 +
{| border="1"  |cellpadding="20" cellspacing="0
 +
|Task
 +
|Time Budget
 +
|-
 +
| (mm) ||  plastic || metal
 +
|-
 
{
 
{
 
|-
 
|-
Beam setup | 0.5 days
+
|Beam setup || 0.5 days
Testing 20 new blocks & 2.5 days\\
+
|-
Silicon test & 1.0 day \\
+
|Testing 20 new blocks || 2.5 days
Bleaching/Re-irradiation test & 0.5-1 day\\
+
|-
Testing old blocks & 12 blocks/day\\
+
|Silicon test || 1.0 day  
 
+
|-
 +
|Bleaching/Re-irradiation test ||  0.5-1 day
 +
|-
 +
|Testing old blocks || 12 blocks/day
 +
|}
  
 
=5/11/09=
 
=5/11/09=

Revision as of 22:43, 27 April 2009

http://clasweb.jlab.org/wiki/index.php/Hall_A_IAC_Tests


Previous Tests: IAC_LeadFlourideCherenkovCrystalTests

Run Plan

Summary

{
Task Time Budget
(mm) plastic metal
Beam setup 0.5 days
Testing 20 new blocks 2.5 days
Silicon test 1.0 day
Bleaching/Re-irradiation test 0.5-1 day
Testing old blocks 12 blocks/day

5/11/09