| − | + | * Vacuum pipe and radiator ladder (design) | |
| − | + | * Graphite block with Pb sheet (design / fabrication) | |
| − | + | * Pb collimator (design / fabrication) | |
| − | + | * d<sub>2</sub>0 target | |
| − | + | * d<sub>2</sub>0 target mount | |
| − | + | * Get n<sup>o</sup> detectors; high voltage (check them out) | |
| − | + | * n<sup>o</sup> detector mount / shielding (design / fabrication) | |
| − | + | * Data acquisition electronics | |
| − | * Discriminators | + | ** Discriminators |
| + | ** Scalers | ||
| + | ** Take the digital pulse, send it into a counter (scaler), and it gives us a number. | ||
| − | * | + | * Callibration procedure |
| − | * | + | * Beam position monitoring |
| − | + | [[Image:ndetector.jpg]] | |
| − | |||
| − | |||
| − | |||
| − | |||
Revision as of 11:52, 3 July 2008
- Vacuum pipe and radiator ladder (design)
- Graphite block with Pb sheet (design / fabrication)
- Pb collimator (design / fabrication)
- d20 target
- d20 target mount
- Get no detectors; high voltage (check them out)
- no detector mount / shielding (design / fabrication)
- Data acquisition electronics
- Discriminators
- Scalers
- Take the digital pulse, send it into a counter (scaler), and it gives us a number.
- Callibration procedure
- Beam position monitoring