Line 70: | Line 70: | ||
[[File:StatusPicS2S3onAframe_2-16-13.jpg | 100 px]][[File:StatusPicS156onAframe_2-16-13.jpg | 100 px]] | [[File:StatusPicS2S3onAframe_2-16-13.jpg | 100 px]][[File:StatusPicS156onAframe_2-16-13.jpg | 100 px]] | ||
+ | |||
+ | =2/20/13= | ||
+ | |||
+ | Moved HV octopus to S6 | ||
+ | |||
+ | Color code | ||
+ | |||
+ | Yellow = Sense | ||
+ | |||
+ | Green= Ground | ||
+ | |||
+ | Black & Blue = Field | ||
+ | |||
+ | Red = Guard | ||
[[CLAS12_R1_Progress_Reports#January_2013]] | [[CLAS12_R1_Progress_Reports#January_2013]] |
Revision as of 18:44, 20 February 2013
2/4/13
Goals:
- number feedthrough on S3
- install S2 onto A-frame
- make protective covers for S5
Installed S2 onto A-Frame along with stringing rail and Magnet.
Half of the feed-throughs were numbered
Finished top cover for S5, crimp pin covers will be worked on tomorrow
2/5/13
Goals:
- Finish numbering feed-throughs on S3
- finish constructing crimp pin covers and window cover
- Install "new" stringing machine on S2
- re-string 5 bent wires from S5
2/6/13
Goal:
- pot S3 wires
- begin wire wrapping S6
2/7/13
Goal:
- finish potting S5
- continue wire wrapping S6
2/11/13
Goal:
- remove S5 from clean room
- Level A-frame
- Install S3 pre-tensioners
2/12/13
Goals:
- Finish installing pre-tensioners on S3
- mount S3 onto A-frame
- Continue wire wrapping S6
- Clean the Clean room to prepare for stringing (vacuum shavings from hoist, clean all wall surfaces, clean A-Frames and DC strong-backs, lifts, both white tables, ladders, computer keyboard)
2/19/13
Goals:
- Change discriminator threshold to -20 mV from -60 mV and start a new run.
- Begin stringing S2
Dropped 25 guard wires to row 20 on S2 SL2
S1,S5,S6 on upper level
S2 on left and S3 on right A-frames
2/20/13
Moved HV octopus to S6
Color code
Yellow = Sense
Green= Ground
Black & Blue = Field
Red = Guard