2/4/13

Goals:

number feedthrough on S3
install S2 onto A-frame
make protective covers for S5


Installed S2 onto A-Frame along with stringing rail and Magnet.

Half of the feed-throughs were numbered

Finished top cover for S5, crimp pin covers will be worked on tomorrow


2/5/13

Goals:

Finish numbering feed-throughs on S3
finish constructing crimp pin covers and window cover
Install "new" stringing machine on S2
re-string 5 bent wires from S5

2/6/13

Goal:

pot S3 wires

2/7/13

Goal:

remove S5 from A-Frame
purge inside of S3 with nitrogen to remove particles before moving to clean room
place S3 on floor of clean room for pre-tensioning
Level A-frame for S3


2/11/13

Goal:

remove S5 from clean room
Level A-frame
Install S3 pre-tensioners

2/12/13

Goals:

Finish installing pre-tensioners on S3
mount S3 onto A-frame
Clean the Clean room to prepare for stringing (vacuum shavings from hoist, clean all wall surfaces, clean A-Frames and DC strong-backs, lifts, both white tables, ladders, computer keyboard)