Difference between revisions of "TF IsotopeTracers"

From New IAC Wiki
Jump to navigation Jump to search
Line 34: Line 34:
 
Equipment list
 
Equipment list
  
 +
=Time line=
  
 +
Time needed to train lead stringer at JLab = 4-6 weeks?
 +
  
 +
{| border="1"  |cellpadding="20" cellspacing="0
 +
|-
 +
| Start Date || End Date || Actually End Date || Description
 +
|-
 +
|  5/17/10  || 9/30/10 || 8/6/10 ||Sign MOU
 +
|-
 +
|  5/17/10  ||9/30/11 ||  4/12/11 || Contract recieved
 +
|-
 +
| 8/3/2010  || 8/3/2010 || 8/18/2011 ||Readiness Review
 +
|-
 +
| 9/1/10  || 10/29/10 || 6/16/2011 ||Hire and train R1 Lead Stringer
 +
|-
 +
| 10/1/10  || 2/28/11 || ||Hire and train 2 R1 stringers
 +
|-
 +
| 11/16/09  || 11/30/10 || ||Build R1 Cleanroom
 +
|-
 +
| 11/5/2010  ||  11/12/2011 || 8/16/2011 ||Ship 1st R1 Box From JLab to ISU
 +
|-
 +
| 12/17/2010  ||  2/28/2011 || ||String First R1 Chambers
 +
|-
 +
|2/21/2011  ||  3/31/2011 || ||Ship remaining R1 Boxes From JLab to ISU
 +
|-
 +
|  ||  3/31/2011 ||1/25/2012 || Fixture and 2 chambers arrive at ISU
 +
|-
 +
|  ||  7/13/12 || ||Complete 6th R1 chamber
 +
|-
 +
|4/5/13  ||  9/30/13 || ||Ship chambers, fixtures, platforms and crane to JLab
 +
|}
  
[[User_talk:Foretony#IAC]]
+
 
 +
{| border="1"  |cellpadding="20" cellspacing="0
 +
|-
 +
| Week ||  Expected Date || Actual Date || Description
 +
|-
 +
|  0 || April 4, 2011 || 4/12/11 || Issue Construction contract
 +
|-
 +
| 4 || May 2,2011||6/13/11 ||Hire lead stringer send to JLab for training
 +
|-
 +
| 14  || July 11, 2011 || August 18, 2011 ||Clean room installed at ISU, Readiness Review, Hire 1st stringing team
 +
|-
 +
|  || || Sept. 26, 2011 ||Begin stringing R1 chamber 2
 +
|-
 +
|  || Nov, 2011 || Dec. 2, 2011  ||[https://wiki.iac.isu.edu/index.php/201112_R1ProgressRep#12.2F2.2F11 Finish guard and field wires on Region 1 Chamber 2]
 +
|-
 +
| 36 || Dec. 12, 2011 || ||Hire and begin training 2nd stringing team
 +
|-
 +
| 40 || Jan. 9, 2012 ||March 20, 2012 ||[https://wiki.iac.isu.edu/index.php/201203_R1ProgressRep#3.2F20.2F12 Begin stringing R1 Chamber 3]
 +
|-
 +
|  ||  March 2, 2012|| Jan. 23, 2012 || [https://wiki.iac.isu.edu/index.php/201201_R1ProgressRep#1.2F23.2F12 Complete stringing  R1 C2 Sector 1]
 +
|-
 +
|  ||  March 14, 2012|| ||Begin stringing  R1 C4 Sector 5
 +
|-
 +
| 45 ||  March 20, 2012|| ||Complete stringing  and wire tests R1 C2
 +
|-
 +
|66  ||Aug 13, 2012 || ||Complete Stringing and wire tests R1 C3
 +
|-
 +
| 71  || Sept 16, 2012 || ||Complete Stringing and wire tests R1 C4
 +
|-
 +
|94 || Feb 25, 2013 || ||Complete Stringing and wire tests R1 C5
 +
|-
 +
| 97  || March 18, 2013|| ||Complete Stringing and wire tests R1 C6
 +
|-
 +
| 104  ||  April 27, 2013 || November, 2014 ||Ship chambers, fixtures, platforms and crane to JLab
 +
|}
 +
 
 +
4 ingredients to contract
 +
 
 +
1.) MOU: Memorandum of Understanding,
 +
 
 +
2.) SOW: Statement of Work
 +
 
 +
3.) Detailed Schedule
 +
 
 +
4.) Sole Source Justification
 +
 
 +
5.) Contact person:  Pre Award Dave Harris? Approve Terms and conditions
 +
 
 +
 
 +
University gets a Purchase Req: covers SOW, Terms & Condition, & Schedule.
 +
 
 +
We

Revision as of 04:08, 2 December 2012

Nitrogen tracers: N-15 is rare. If you dope nitrogen sources with it you can see where the leak into environment. This is a stable tracer so it would be able to monitor long time plume expansions.

Catchment hydrology


High Flux MeV photon profiler

http://accelconf.web.cern.ch/accelconf/p99/PAPERS/WEA90.PDF

http://ieeexplore.ieee.org/ielx5/5379507/5398121/05398374.pdf?tp=&arnumber=5398374&isnumber=5398121

CVD Diamond film

Film Vendor only

http://www.e6cvd.com/cvd/page.jsp?pageid=415

Alemeda Applied Sciences Corporation

http://www.aasc.net/drds http://www.aasc.net/media/DRD-AppNote.pdf

Diamond x-ray view screen http://www.diamond-materials.com/EN/products/cvd_for_xray/fluorescence_beam_monitors.htm

http://www.npl.co.uk/upload/pdf/091104_nuc_galbiati.pdf

NIM paper from 2002

http://www.npl.co.uk/upload/pdf/091104_nuc_galbiati.pdf

Budget

Equipment list

Time line

Time needed to train lead stringer at JLab = 4-6 weeks?


Start Date End Date Actually End Date Description
5/17/10 9/30/10 8/6/10 Sign MOU
5/17/10 9/30/11 4/12/11 Contract recieved
8/3/2010 8/3/2010 8/18/2011 Readiness Review
9/1/10 10/29/10 6/16/2011 Hire and train R1 Lead Stringer
10/1/10 2/28/11 Hire and train 2 R1 stringers
11/16/09 11/30/10 Build R1 Cleanroom
11/5/2010 11/12/2011 8/16/2011 Ship 1st R1 Box From JLab to ISU
12/17/2010 2/28/2011 String First R1 Chambers
2/21/2011 3/31/2011 Ship remaining R1 Boxes From JLab to ISU
3/31/2011 1/25/2012 Fixture and 2 chambers arrive at ISU
7/13/12 Complete 6th R1 chamber
4/5/13 9/30/13 Ship chambers, fixtures, platforms and crane to JLab


Week Expected Date Actual Date Description
0 April 4, 2011 4/12/11 Issue Construction contract
4 May 2,2011 6/13/11 Hire lead stringer send to JLab for training
14 July 11, 2011 August 18, 2011 Clean room installed at ISU, Readiness Review, Hire 1st stringing team
Sept. 26, 2011 Begin stringing R1 chamber 2
Nov, 2011 Dec. 2, 2011 Finish guard and field wires on Region 1 Chamber 2
36 Dec. 12, 2011 Hire and begin training 2nd stringing team
40 Jan. 9, 2012 March 20, 2012 Begin stringing R1 Chamber 3
March 2, 2012 Jan. 23, 2012 Complete stringing R1 C2 Sector 1
March 14, 2012 Begin stringing R1 C4 Sector 5
45 March 20, 2012 Complete stringing and wire tests R1 C2
66 Aug 13, 2012 Complete Stringing and wire tests R1 C3
71 Sept 16, 2012 Complete Stringing and wire tests R1 C4
94 Feb 25, 2013 Complete Stringing and wire tests R1 C5
97 March 18, 2013 Complete Stringing and wire tests R1 C6
104 April 27, 2013 November, 2014 Ship chambers, fixtures, platforms and crane to JLab

4 ingredients to contract

1.) MOU: Memorandum of Understanding,

2.) SOW: Statement of Work

3.) Detailed Schedule

4.) Sole Source Justification

5.) Contact person: Pre Award Dave Harris? Approve Terms and conditions


University gets a Purchase Req: covers SOW, Terms & Condition, & Schedule.

We