Difference between revisions of "PePPO 2012Run"
Jump to navigation
Jump to search
(Created page with ' Jan 22, 2012 Readiness Review Positrons') |
|||
| Line 1: | Line 1: | ||
| + | Jan 22, 2012 Readiness Review | ||
| + | |||
| + | |||
| + | Currently scheduled Injector recovery on October 22 | ||
| + | |||
| + | Positrons May be November 4 & 5 | ||
| + | |||
| + | |||
| + | Currently max energy is 7.8 MeV. | ||
| + | |||
| + | |||
| + | Choosing 6.3 MeV incident electron energy because that is the most stable. | ||
| + | |||
| + | <math>\sigma</math> = 0.5 mm on the Tungsten target (T1) | ||
| + | |||
| − | + | ||
| + | {| border="1" |cellpadding="20" cellspacing="0 | ||
| + | |- | ||
| + | |June || Racks installed and cables pulled to tunnel | ||
| + | |- | ||
| + | |August 2011 || vacuum pumps ready, Compton Polarimeter Table installed | ||
| + | |- | ||
| + | |September 2011 || Beam Line installed | ||
| + | |- | ||
| + | |October 2011 || Finish Work in Injector area for PePPO | ||
| + | |- | ||
| + | |October 17-19, 2011 || Swing shift hot checkout | ||
| + | |- | ||
| + | |October 29-Nov 1 2011 || Owl shift PePPo tuning (Probably install Annihilation counter here) | ||
| + | |- | ||
| + | |Nov 11-16 2011 || Day shift PePPo running | ||
| + | |- | ||
| + | |} | ||
[[Positrons]] | [[Positrons]] | ||
Revision as of 15:58, 23 November 2011
Jan 22, 2012 Readiness Review
Currently scheduled Injector recovery on October 22
Positrons May be November 4 & 5
Currently max energy is 7.8 MeV.
Choosing 6.3 MeV incident electron energy because that is the most stable.
= 0.5 mm on the Tungsten target (T1)
| June | Racks installed and cables pulled to tunnel |
| August 2011 | vacuum pumps ready, Compton Polarimeter Table installed |
| September 2011 | Beam Line installed |
| October 2011 | Finish Work in Injector area for PePPO |
| October 17-19, 2011 | Swing shift hot checkout |
| October 29-Nov 1 2011 | Owl shift PePPo tuning (Probably install Annihilation counter here) |
| Nov 11-16 2011 | Day shift PePPo running |