Jan 22, 2012  Readiness Review
 +
 +
 +
Currently scheduled Injector recovery on October 22
 +
 +
Positrons May be November 4 & 5
 +
 +
 +
Currently max energy is 7.8 MeV.
 +
 +
 +
Choosing 6.3 MeV incident electron energy because that is the most stable.
 +
 +
<math>\sigma</math> = 0.5 mm on the Tungsten target (T1)
 +
  
Jan 22, 2012  Readiness Review
+
 
 +
{| border="1"  |cellpadding="20" cellspacing="0
 +
|-
 +
|June || Racks installed and cables pulled to tunnel
 +
|-
 +
|August 2011 || vacuum pumps ready, Compton Polarimeter Table installed
 +
|-
 +
|September 2011 || Beam Line installed
 +
|-
 +
|October 2011 || Finish Work in Injector area for PePPO
 +
|-
 +
|October 17-19, 2011 || Swing shift hot checkout
 +
|-
 +
|October 29-Nov 1 2011 || Owl shift PePPo tuning (Probably install Annihilation counter here)
 +
|-
 +
|Nov 11-16 2011 || Day shift PePPo running
 +
|-
 +
|}
  
  
 
[[Positrons]]
 
[[Positrons]]

Revision as of 15:58, 23 November 2011

Jan 22, 2012 Readiness Review


Currently scheduled Injector recovery on October 22

Positrons May be November 4 & 5


Currently max energy is 7.8 MeV.


Choosing 6.3 MeV incident electron energy because that is the most stable.

[math]\sigma[/math] = 0.5 mm on the Tungsten target (T1)


June Racks installed and cables pulled to tunnel
August 2011 vacuum pumps ready, Compton Polarimeter Table installed
September 2011 Beam Line installed
October 2011 Finish Work in Injector area for PePPO
October 17-19, 2011 Swing shift hot checkout
October 29-Nov 1 2011 Owl shift PePPo tuning (Probably install Annihilation counter here)
Nov 11-16 2011 Day shift PePPo running


Positrons