Alignment
Timeline
| Completion Date | Task |
| 4/29/11 | remove HRRL Gun |
| 5/2/2011 | Install alignment laser |
| 5/3/2011 | Install rotation and translation stages |
| 5/9/2011 | Align zero degree beam line |
| 5/12/2011 | Align 45 degree beam line |
| 5/13/2011 | Align 90 degree beam line |
Procedure
Equipment
Precision Rotation Stage
Thor Labs 1 arc sec resolution, 5 arc min accuracy, Rotator $2425, APT controller $1600,
Elliot Scientific Manual rotation, 5 arc sec resolution, $600