+ | == Design and build required infrastructure== | ||
+ | |||
+ | |||
+ | === Beam line CAD=== | ||
+ | |||
+ | The location of all magnets is provided by Yujong Kim. | ||
+ | |||
+ | Kevin Folkman will layout the CAD drawings | ||
+ | |||
+ | === Accelerator Wall Mount=== | ||
+ | |||
+ | A mounting system needs to be designed for the HRRL which will be used for its new position. It is unclear if we can reuse the current stands. We will want a way to add lead sheets around the HRRL and the location of the Tungsten converter target which is after the first 3 quads and labeled (PT) in the drawings. | ||
+ | |||
+ | |||
+ | === Stands=== | ||
+ | |||
+ | Chad has built one stand to hold 3 Quads. We will need 3 more stand built to hold quad triples and 2 stands to hold the "Kiwi" dipoles. | ||
+ | |||
+ | === FC cooling=== | ||
+ | |||
+ | We need to solder cooling lines around the FC. | ||
+ | |||
+ | == Move the HRRL== | ||
+ | === Alignment === | ||
+ | |||
+ | Khalid, Sadiq, and IAC theodolite operator. | ||
1.) Alignment: | 1.) Alignment: | ||
a.) spare gun | a.) spare gun | ||
b.) laser with targets mounted on wall. | b.) laser with targets mounted on wall. | ||
− | |||
− | |||
=Design preference= | =Design preference= | ||
Thin aluminum target for OTR right after 3 quads place at exit to Linac | Thin aluminum target for OTR right after 3 quads place at exit to Linac |
Revision as of 15:04, 2 September 2010
Timeline
Start Date | Finish Date | Task |
10/01/10 | 11/01/10 | Move the HRRL and construct new beamline |
11/01/10 | 11/15/10 | Measure Radiation Field and Prepare for Hunt Run |
11/15/10 | 12/17/10 | Hunt Beam Time (3 MeV, 300 Hz, multiple pulsing) |
01/03/10 | 01/14/10 | Prepare for high current emmittance measurements |
01/18/10 | 01/21/10 | high current emmittance measurements (10 MeV, 50 ns pulse width, variable rep rate and current) |
Tasks
Design and build required infrastructure
Beam line CAD
The location of all magnets is provided by Yujong Kim.
Kevin Folkman will layout the CAD drawings
Accelerator Wall Mount
A mounting system needs to be designed for the HRRL which will be used for its new position. It is unclear if we can reuse the current stands. We will want a way to add lead sheets around the HRRL and the location of the Tungsten converter target which is after the first 3 quads and labeled (PT) in the drawings.
Stands
Chad has built one stand to hold 3 Quads. We will need 3 more stand built to hold quad triples and 2 stands to hold the "Kiwi" dipoles.
FC cooling
We need to solder cooling lines around the FC.
Move the HRRL
Alignment
Khalid, Sadiq, and IAC theodolite operator. 1.) Alignment: a.) spare gun b.) laser with targets mounted on wall.
Design preference
Thin aluminum target for OTR right after 3 quads place at exit to Linac