Line 145: | Line 145: | ||
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards, | other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards, | ||
− | =7/ | + | =7/22/13= |
− | Dion: String S2 with David | + | Dion: String S2 with David , left 1 hour early |
− | David: String S2 with Dion | + | David: String S2 with Dion , left 1 hour early |
− | Debbie: String S3 | + | Debbie: String S3, left 1 hour early |
Haitham: HV burn in S5 and test signals | Haitham: HV burn in S5 and test signals | ||
Line 163: | Line 163: | ||
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards, | other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards, | ||
+ | |||
+ | =7/23/13= | ||
+ | |||
+ | Dion: String S2 with David | ||
+ | |||
+ | David: String S2 with Dion , starting at 8:30 am | ||
+ | |||
+ | Debbie: String S3, sick day | ||
+ | |||
+ | Haitham: HV burn in S5 and test signals | ||
+ | |||
+ | Carlos: wire tension measurements, work on analyzing data to determine efficiency | ||
+ | |||
+ | |||
+ | S2: on Sense wire row 61 | ||
+ | |||
+ | S3: on Sense wire row 88 | ||
+ | |||
+ | other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards, | ||
+ | |||
+ | =7/24/13= | ||
+ | |||
+ | Dion: String S2 with David | ||
+ | |||
+ | David: String S2 with Dion | ||
+ | |||
+ | Debbie: String S3 | ||
+ | |||
+ | Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5 | ||
+ | |||
+ | Carlos: wire tension measurements, work on analyzing data to determine efficiency | ||
+ | |||
+ | |||
+ | S2: on Sense wire row 61 | ||
+ | |||
+ | S3: on Sense wire row 88 | ||
+ | |||
+ | other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards, | ||
+ | |||
+ | |||
+ | =7/24/13= | ||
+ | |||
+ | Dion: String S2 with David | ||
+ | |||
+ | David: String S2 with Dion | ||
+ | |||
+ | Debbie: String S3 | ||
+ | |||
+ | Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5 | ||
+ | |||
+ | |||
+ | [[S6 Testing and Performance Summary]] | ||
+ | |||
+ | |||
+ | Carlos: wire tension measurements, work on analyzing data to determine efficiency | ||
+ | |||
+ | |||
+ | S2: on Sense wire row 109 | ||
+ | |||
+ | S3: on Sense wire row 129 | ||
[[CLAS12_R1_Progress_Reports]] | [[CLAS12_R1_Progress_Reports]] |
Latest revision as of 16:23, 4 August 2013
7/04/13
Clean room HVAC Low temperature alarm went off. Charts show that at 4am the temperature started dropping from 68 to 66 at noon.
Changed set point from 67 to 68.
The temperature monitor indicates that the temperatures went back to 70 degrees by 8pm.
crimpers are gapped at 0.03" (0.765 mm) every hour
7/08/13
Dion: String S3 with Debbie, taking afternoon off
Haitham: String S2 with David
David: String S2 with Haitham, install octopus on S5 SL2 and start HV burn in
Debbie: String S3 with Dion
Carlos: wire tension measurments, work on analyzing data to determine efficiency
S2: on Sense wire row 109
S3: on Sense wire row 163
S5, guard, crimped part was 0.043", uncrimped pin 0.065 ".
7/09/13
Dion: Solder HV boards & look for S5SL1 signals, String S3 with David in the afternoon
Haitham: String S2 with David
David: String S2 with Haitham in the morning S3 with Dion in the afternoon
Debbie: day off
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row 130
S3: on Sense wire row 182
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/10/13
Dion: String S3 with David
Haitham: String S2 with Debbie
David: String S2 with Dion
Debbie: String S2 with Haitham
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row
S3: on Sense wire row
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/15/13
Dion: String S2 with David
David: String S2 with Dion
Debbie: String S3
Haitham: HV burn in S5 and test signals
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row 184
S3: on Sense wire row 2 (on the last super layer)
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/16/13
Dion: String S2 with David , took afternoon off
David: String S2 with Dion
Debbie: String S3
Haitham: HV burn in S5 and test signals
Carlos: wire tension measurements, work on analyzing data to determine efficiency
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/17/13
Dion: String S2 with David
David: String S2 with Dion
Debbie: started String S3 at 9am
Haitham: HV burn in S5 and test signals
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row 3 SL1 (Last superlayer)
S3: on Sense wire row 38
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/18/13
Dion: String S2 with David
David: String S2 with Dion
Debbie: started String S3
Haitham: HV burn in S5 and test signals
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row 16
S3: on Sense wire row 58
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/22/13
Dion: String S2 with David , left 1 hour early
David: String S2 with Dion , left 1 hour early
Debbie: String S3, left 1 hour early
Haitham: HV burn in S5 and test signals
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row 37
S3: on Sense wire row 69
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/23/13
Dion: String S2 with David
David: String S2 with Dion , starting at 8:30 am
Debbie: String S3, sick day
Haitham: HV burn in S5 and test signals
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row 61
S3: on Sense wire row 88
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/24/13
Dion: String S2 with David
David: String S2 with Dion
Debbie: String S3
Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row 61
S3: on Sense wire row 88
other tasks: summary table of S6 signals (which wires are hot,...), solder HV boards,
7/24/13
Dion: String S2 with David
David: String S2 with Dion
Debbie: String S3
Haitham: HV burn in S5 and test signals, debug TDC DAQ, S6 summary table and pictures, debug high current on S5-SL2-HVB5
S6 Testing and Performance Summary
Carlos: wire tension measurements, work on analyzing data to determine efficiency
S2: on Sense wire row 109
S3: on Sense wire row 129