Difference between revisions of "201403 R1ProgressRep"
Line 96: | Line 96: | ||
6.) pre-tensioning hardware, any leftover wire and parts | 6.) pre-tensioning hardware, any leftover wire and parts | ||
+ | =March 28 2014= | ||
+ | |||
+ | |||
+ | Crane and forklift arrive at 1:30 this afternoon to move equipment over to loading dock. | ||
+ | |||
+ | Two drift chambers go on the loading dock in the same spot used last time | ||
+ | |||
+ | The man lifts, A-fram and any other equipment goes in the shops area across the driveway front eh loading dock. | ||
+ | |||
[[CLAS12_R1_Progress_Reports#March_2014]] | [[CLAS12_R1_Progress_Reports#March_2014]] |
Revision as of 16:15, 21 March 2014
March 7 2014
- Delays prevented Windows from being installed. They should be installed this weekend.
- Final plugs and standoffs will be glued in today
- remove chamber from clean room Sunday
- Get shipping pallets for lifts, A-frames, the last chamber, and small equipment
- Schedule pickup for Friday March 28 so the chamber arrives at JLab during the following week
Plan is to wire wrap, install boards, HV test to 100 Volts in air, and install board covers.
Get Carriage bolts for drift chamber lifting frame
Check that brass screws for windows are in.
Shrink wrap for the last two chambers.
Information to find:
A-frame dimensions:
- Base Width (dimension perpendicular to the rotation cylinder): 57"
- Base Depth (dimension parallel to cylinder): 52"
- Base Depth (including mounting points at top): 68"
- A-frame plumb (vertical) height: 79"
Note: vertical height includes the height added by a metal end-piece that connects to the cylinder's mounts.
- A-frame side-length (structural member connecting base to top of "A"): 84"
- Carriage bolt length for nose-piece of chamber lifting structure: 5.25" long, 1" coarse thread
March 8 2014
Installation of mylar windows complete. All plugs and plastic stand-offs installed.
March 19 2014
- Wire wrap is ~70% done
- 2 suspension boots installed on chamber pallets.
March 20 2014
- Wire wrap is ~85% done
- All suspension boots installed on pallets. A-frame pallet is finished.
Remaining tasks:
HV Testing
- Segment wire-wrap
- Install HV boards, conductive boots & the 'kraken'
- Do 100/50/20V test on wire-types to check for crossed-wires & excess current draw (what's our metric for success w/ current draw? 10 micro-amps?)
Assuming no problems with HV testing...
- Try placing a chamber onto a suspension-boot pallet. (do we want to try both chambers? do they need to be packaged first?)
- Cut and install 3mil dust covers on S2, Re-do dust cover on one side of S1 (it's been sliced open and isn't repairable)
- Move A-frame out of clean-room and onto a pallet. (store outside) (how do we strap down the A-frame & cylinder? Is there a particular method?)
- Move both scissor-lifts out and onto pallets.
- Organize miscellaneous lab materials for shipping back to J-lab on pallets. (need the metal-strap crimping device back)
- Put padding/bubble-wrap back on the extra set of HV boards we didn't install before shipping.
March 24 2014
If HV test passed, && Dust covers are one:
Goal: Finish boxing up drift chamber so they are ready to be mount onto the pallets (check that they go into the boots)
March 25 2014
Prepare A-Frame for shipping by putting it on a pallet and placing it outside the basement door.
March 26 2014
Strap both blue man lifts onto separate pallets.
March 27 2014
Pack everything else onto pallets that can move out using the elevator.
prioritized list
1.) both magnets onto pallets 2.) stringing machine and power supply, potting machine, special crimpers cutters and other tools. 3.)Post amp for DC signals needs to be boxed up and sent back 4.) Box up VME amplifiers and other DAQ related equipment (NOT the TDC) 5.) function generator used for tension measurements, 6.) pre-tensioning hardware, any leftover wire and parts
March 28 2014
Crane and forklift arrive at 1:30 this afternoon to move equipment over to loading dock.
Two drift chambers go on the loading dock in the same spot used last time
The man lifts, A-fram and any other equipment goes in the shops area across the driveway front eh loading dock.