Difference between revisions of "AW CLAS12R1"
Jump to navigation
Jump to search
Line 17: | Line 17: | ||
;11/16/2013 | ;11/16/2013 | ||
:Confirmed signals on S5 SL2 sense wires. Found eight wires not listed in [[S5 Testing and Performance Summary]] without signal. Will test again to verify. | :Confirmed signals on S5 SL2 sense wires. Found eight wires not listed in [[S5 Testing and Performance Summary]] without signal. Will test again to verify. | ||
− | |||
− | |||
:SL2 has been in HV burnin: S:F:G = 1500:-750:536 and the current draw is 1-2 uA on the sense wires. Has not gone down after a week. | :SL2 has been in HV burnin: S:F:G = 1500:-750:536 and the current draw is 1-2 uA on the sense wires. Has not gone down after a week. | ||
Revision as of 16:53, 5 December 2013
11/1/2013
- Goals
- Confirm signals on all of Sector 5's sense wires
- Finish HV burnin: S:F:G = 1500:-750:536 and the current draw is less than 1 uA CLAS12_R1_S5_QA
- After the above is completed, stop gas flow, Install dust covers, prepare for shipping
- Test TDC integrity using DAQ and S1
- 11/8/2013
- Worked with Haitham on Sector 5
- Moved Kraken to SL2
- Began confirming signals on S5 sense wires S5 Testing and Performance Summary
- Add missing oscilloscope image SL2-STB6-K1200872 U10
- Confirmed with Haitham that HV burin is completed for SL2 R1S5_SL2_BurnIn
- Rotated Sector 3 with David
- 11/16/2013
- Confirmed signals on S5 SL2 sense wires. Found eight wires not listed in S5 Testing and Performance Summary without signal. Will test again to verify.
- SL2 has been in HV burnin: S:F:G = 1500:-750:536 and the current draw is 1-2 uA on the sense wires. Has not gone down after a week.
- 11/21/2013
- The 2 Fold HV Power Supply still reading between 1-2 uA. Could be readout on power supply. According to Wiki the burnin for S5 SL2 is complete.
- Retested signals on eight wires not listed in Testing Summary for signal that were found without signal. Could get signal on five of the wires checked.
- Available times
- Monday 9-5
- T,Th 9-3
- W,F 12-5
Weekly progress meeting at 10 am Mondays