#After the above is completed, stop gas flow, Install dust covers, prepare for shipping
 
#After the above is completed, stop gas flow, Install dust covers, prepare for shipping
 
#Test TDC integrity using DAQ and S1
 
#Test TDC integrity using DAQ and S1
 +
 +
11/8/2013
 +
Worked with Haitham on Sector 5
 +
    Moved Kraken to SL2
 +
    Began confirming signals on S5 sense wires
 +
    Add missing oscilloscope image SL2-STB6-K1200872 U10
 +
Confirmed with Haitham that HV burin is completed for SL2
 +
Rotated Sector 3 with David
  
 
;Available times
 
;Available times

Revision as of 16:13, 11 November 2013

11/1/2013

Goals
  1. Confirm signals on all of Sector 5's sense wires
  2. Finish HV burnin: S:F:G = 1500:-750:536 and the current draw is less than 1 uA CLAS12_R1_S5_QA
  3. After the above is completed, stop gas flow, Install dust covers, prepare for shipping
  4. Test TDC integrity using DAQ and S1

11/8/2013 Worked with Haitham on Sector 5

    Moved Kraken to SL2
    Began confirming signals on S5 sense wires
    Add missing oscilloscope image SL2-STB6-K1200872 U10

Confirmed with Haitham that HV burin is completed for SL2 Rotated Sector 3 with David

Available times
Monday 9-5
T,Th 9-3
W,F 12-5


Weekly progress meeting at 10 am Mondays