Difference between revisions of "40MeV BeamLineInstall 10252013"
Jump to navigation
Jump to search
| (5 intermediate revisions by the same user not shown) | |||
| Line 4: | Line 4: | ||
3 week lead time on flanges | 3 week lead time on flanges | ||
| + | |||
| + | goal will be to run on Dec 2 or Dec 9. | ||
==Without 6 cross== | ==Without 6 cross== | ||
| Line 19: | Line 21: | ||
| 335 || non-rotatable flanges | | 335 || non-rotatable flanges | ||
|- | |- | ||
| − | | | + | | 329+282+141 || 7' + 6' + 3' SS pipe lengths |
|- | |- | ||
| 250 || turning pipe on lathe | | 250 || turning pipe on lathe | ||
|- | |- | ||
| − | | 2400 || 2 days of labor building beam line and 1 day installation | + | | 2400 || 2 days of labor building beam line components and 1 day installation |
|} | |} | ||
| Line 33: | Line 35: | ||
|- | |- | ||
| 0 || 5 mil exit window | | 0 || 5 mil exit window | ||
| + | |- | ||
| + | | 0 || 338 cube for 6 cross (2" pipe max diameter) | ||
|- | |- | ||
| 221|| glass exit window for beam view screen | | 221|| glass exit window for beam view screen | ||
| Line 40: | Line 44: | ||
| 268 || 4 non-rotatable flanges | | 268 || 4 non-rotatable flanges | ||
|- | |- | ||
| − | | | + | | 47 || 6 " SS beam pipe |
|- | |- | ||
| 800 || 1 day of labor building 6 way cross | | 800 || 1 day of labor building 6 way cross | ||
Latest revision as of 21:49, 28 October 2013
Beam Line Budget
3 week lead time on flanges
goal will be to run on Dec 2 or Dec 9.
Without 6 cross
| Cost ($) | Description |
| 318 | Bellows |
| 158 | Hardware (nuts & bolts) |
| 290 | 5 rotatable flanges |
| 335 | non-rotatable flanges |
| 329+282+141 | 7' + 6' + 3' SS pipe lengths |
| 250 | turning pipe on lathe |
| 2400 | 2 days of labor building beam line components and 1 day installation |
With 6 cross
| Cost ($) | Description |
| 0 | 5 mil exit window |
| 0 | 338 cube for 6 cross (2" pipe max diameter) |
| 221 | glass exit window for beam view screen |
| 232 | 4 rotatable flanges |
| 268 | 4 non-rotatable flanges |
| 47 | 6 " SS beam pipe |
| 800 | 1 day of labor building 6 way cross |