Difference between revisions of "40MeV BeamLineInstall 10252013"
Jump to navigation
Jump to search
(6 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
=Beam Line Budget= | =Beam Line Budget= | ||
+ | |||
+ | |||
+ | 3 week lead time on flanges | ||
+ | |||
+ | goal will be to run on Dec 2 or Dec 9. | ||
==Without 6 cross== | ==Without 6 cross== | ||
Line 16: | Line 21: | ||
| 335 || non-rotatable flanges | | 335 || non-rotatable flanges | ||
|- | |- | ||
− | | | + | | 329+282+141 || 7' + 6' + 3' SS pipe lengths |
|- | |- | ||
| 250 || turning pipe on lathe | | 250 || turning pipe on lathe | ||
|- | |- | ||
− | | 2400 || 2 days of labor building beam line and 1 day installation | + | | 2400 || 2 days of labor building beam line components and 1 day installation |
|} | |} | ||
Line 30: | Line 35: | ||
|- | |- | ||
| 0 || 5 mil exit window | | 0 || 5 mil exit window | ||
+ | |- | ||
+ | | 0 || 338 cube for 6 cross (2" pipe max diameter) | ||
|- | |- | ||
| 221|| glass exit window for beam view screen | | 221|| glass exit window for beam view screen | ||
Line 37: | Line 44: | ||
| 268 || 4 non-rotatable flanges | | 268 || 4 non-rotatable flanges | ||
|- | |- | ||
− | | | + | | 47 || 6 " SS beam pipe |
|- | |- | ||
| 800 || 1 day of labor building 6 way cross | | 800 || 1 day of labor building 6 way cross |
Latest revision as of 21:49, 28 October 2013
Beam Line Budget
3 week lead time on flanges
goal will be to run on Dec 2 or Dec 9.
Without 6 cross
Cost ($) | Description |
318 | Bellows |
158 | Hardware (nuts & bolts) |
290 | 5 rotatable flanges |
335 | non-rotatable flanges |
329+282+141 | 7' + 6' + 3' SS pipe lengths |
250 | turning pipe on lathe |
2400 | 2 days of labor building beam line components and 1 day installation |
With 6 cross
Cost ($) | Description |
0 | 5 mil exit window |
0 | 338 cube for 6 cross (2" pipe max diameter) |
221 | glass exit window for beam view screen |
232 | 4 rotatable flanges |
268 | 4 non-rotatable flanges |
47 | 6 " SS beam pipe |
800 | 1 day of labor building 6 way cross |