Difference between revisions of "40MeV BeamLineInstall 10252013"

From New IAC Wiki
Jump to navigation Jump to search
 
(7 intermediate revisions by the same user not shown)
Line 1: Line 1:
  
 
=Beam Line Budget=
 
=Beam Line Budget=
 +
 +
 +
3 week lead time on flanges
 +
 +
goal will be to run on Dec 2 or Dec 9.
  
 
==Without 6 cross==
 
==Without 6 cross==
Line 16: Line 21:
 
|  335  || non-rotatable flanges
 
|  335  || non-rotatable flanges
 
|-
 
|-
|   || 7' + 6' + 3' SS pipe lengths
+
| 329+282+141  || 7' + 6' + 3' SS pipe lengths
 
|-
 
|-
 
|  250  || turning pipe on lathe  
 
|  250  || turning pipe on lathe  
 
|-
 
|-
|  2400  || 2 days of labor building beam line and 1 day installation
+
|  2400  || 2 days of labor building beam line components and 1 day installation
 
|}
 
|}
  
Line 27: Line 32:
 
{| border="1"  |cellpadding="20" cellspacing="0  
 
{| border="1"  |cellpadding="20" cellspacing="0  
 
|-
 
|-
|Energy (MeV) || dE/dx for e- (MeV/cm)|| dE/dx for e+ (MeV/cm)
+
|Cost ($)||Description
 +
|-
 +
|  0  || 5 mil  exit window
 +
|-
 +
|  0  || 338 cube for 6 cross (2" pipe max diameter)
 +
|-
 +
| 221|| glass exit  window for beam view screen
 +
|-
 +
|  232  || 4 rotatable flanges
 
|-
 
|-
8    || 4.54 +/- 1.05 || 4.40  +/- 1.03
+
268  || 4 non-rotatable flanges
 
|-
 
|-
5    || 4.36 +/- 1.11 ||  4.22 +/- 1.08
+
|   47 || 6 " SS beam pipe
 
|-
 
|-
| 3   || 4.12 +/- 1.19 || 4.03 +/- 1.16
+
800 || 1 day of labor building 6 way cross
 
|}
 
|}
  
  
 
[[Positrons_Using_40Mev_Linac#10.2F14.2F13]]
 
[[Positrons_Using_40Mev_Linac#10.2F14.2F13]]

Latest revision as of 21:49, 28 October 2013

Beam Line Budget

3 week lead time on flanges

goal will be to run on Dec 2 or Dec 9.

Without 6 cross

Cost ($) Description
318 Bellows
158 Hardware (nuts & bolts)
290 5 rotatable flanges
335 non-rotatable flanges
329+282+141 7' + 6' + 3' SS pipe lengths
250 turning pipe on lathe
2400 2 days of labor building beam line components and 1 day installation

With 6 cross

Cost ($) Description
0 5 mil exit window
0 338 cube for 6 cross (2" pipe max diameter)
221 glass exit window for beam view screen
232 4 rotatable flanges
268 4 non-rotatable flanges
47 6 " SS beam pipe
800 1 day of labor building 6 way cross


Positrons_Using_40Mev_Linac#10.2F14.2F13