Beam Line Budget
3 week lead time on flanges
goal will be to run on Dec 2 or Dec 9.
Without 6 cross
| Cost ($) | Description | 
| 318 | Bellows | 
| 158 | Hardware (nuts & bolts) | 
| 290 | 5 rotatable flanges | 
| 335 | non-rotatable flanges | 
| 7' + 6' + 3' SS pipe lengths | |
| 250 | turning pipe on lathe | 
| 2400 | 2 days of labor building beam line components and 1 day installation | 
With 6 cross
| Cost ($) | Description | 
| 0 | 5 mil exit window | 
| 0 | 338 cube for 6 cross (2" pipe max diameter) | 
| 221 | glass exit window for beam view screen | 
| 232 | 4 rotatable flanges | 
| 268 | 4 non-rotatable flanges | 
| 6 " SS beam pipe | |
| 800 | 1 day of labor building 6 way cross |